Wind power plant, Oklahoma
25 Mile Creek wind power plant, Oklahoma
25 Mile Creek is a 250 MW wind power plant in Ellis County, Oklahoma, operated by Enel Green Power NA, Inc., and it generated 1,062,225 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.2% of the generation reported in Oklahoma, and its capacity factor sits at the 97th percentile of U.S. wind plants. By 2025 generation it ranks 708th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the 25 Mile Creek plant run compared with other wind plants?
The 25 Mile Creek plant had a capacity factor of 49% in 2025 on 250 MW of net summer capacity, the 97th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 177 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| 25 Mile Creek | 49% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the 25 Mile Creek plant generating more or less than last year?
Generation at 25 Mile Creek fell 3.9% from 2024 to 2025, from 1,105,758 MWh to 1,062,225 MWh. Through August 2026 it is running 7.8% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 1,105,758 |
| 2025 | 1,062,225 |
| 2026 through August | 769,542 |
| 2025, same months | 714,148 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 91,315 |
| July 2026 | 84,540 |
| June 2026 | 86,820 |
| May 2026 | 92,672 |
| April 2026 | 115,046 |
| March 2026 | 112,471 |
| February 2026 | 89,067 |
| January 2026 | 97,611 |
| December 2025 | 83,483 |
| November 2025 | 88,268 |
| October 2025 | 99,554 |
| September 2025 | 76,772 |
| August 2025 | 70,414 |
| July 2025 | 89,167 |
| June 2025 | 92,784 |
| May 2025 | 79,822 |
| April 2025 | 97,985 |
| March 2025 | 112,703 |
| February 2025 | 87,735 |
| January 2025 | 83,538 |
| December 2024 | 98,055 |
| November 2024 | 104,014 |
| October 2024 | 84,418 |
| September 2024 | 77,112 |
| August 2024 | 77,720 |
| July 2024 | 90,837 |
| June 2024 | 98,951 |
| May 2024 | 87,135 |
| April 2024 | 117,044 |
| March 2024 | 80,003 |
| February 2024 | 106,583 |
| January 2024 | 83,886 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the 25 Mile Creek plant, and when do they retire?
1 operable generator totals 250 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 250 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 44444 | Operating | Onshore Wind Turbine | 250 | 2023 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the 25 Mile Creek plant?
Enel Kansas, LLC is the only joint owner reported for 25 Mile Creek, with 100.0%. Enel Green Power NA, Inc. operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the 25 Mile Creek plant?
25 Mile Creek is in Gage, Ellis County, Oklahoma, at 36.4870° N, 99.7390° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Oklahoma are similar in size?
Oklahoma has 69 operable wind plants with 13,344 MW of capacity, and 25 Mile Creek's 250 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Thunder Ranch Wind Project | Noble | 298 | 805,226 |
| Canadian Hills Wind | Canadian | 294 | 446,009 |
| Maverick Wind Project, LLC | Major | 288 | 855,476 |
| 25 Mile Creek | Ellis | 250 | 1,062,225 |
| Rush Springs Wind | Stephens | 250 | 902,240 |
| King Plains Wind Project | Garfield | 248 | 592,686 |
| Armadillo Flats Wind Project, LLC | Garfield | 247 | 750,143 |
Source: EIA Forms EIA-860 and EIA-923, 2025.