Wind power plant, Oklahoma
Thunder Ranch Wind Project, Oklahoma
Thunder Ranch Wind Project is a 298 MW wind power plant in Noble County, Oklahoma, operated by Thunder Ranch Wind Project, LLC, and it generated 805,226 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.9% of the generation reported in Oklahoma, and its capacity factor sits at the 43rd percentile of U.S. wind plants. By 2025 generation it ranks 871st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Thunder Ranch Wind Project plant run compared with other wind plants?
The Thunder Ranch Wind Project plant had a capacity factor of 31% in 2025 on 298 MW of net summer capacity, the 43rd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 113 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Thunder Ranch Wind Project | 31% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Thunder Ranch Wind Project plant generating more or less than last year?
Generation at Thunder Ranch Wind Project fell 21.5% from 2024 to 2025, from 1,026,182 MWh to 805,226 MWh. Through August 2026 it is running 40.7% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 1,026,182 |
| 2025 | 805,226 |
| 2026 through August | 746,283 |
| 2025, same months | 530,223 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 96,961 |
| July 2026 | 71,787 |
| June 2026 | 102,129 |
| May 2026 | 84,102 |
| April 2026 | 116,649 |
| March 2026 | 115,396 |
| February 2026 | 64,257 |
| January 2026 | 95,002 |
| December 2025 | 92,630 |
| November 2025 | 56,393 |
| October 2025 | 75,646 |
| September 2025 | 50,334 |
| August 2025 | 62,055 |
| July 2025 | 81,557 |
| June 2025 | 45,143 |
| May 2025 | 59,287 |
| April 2025 | 51,417 |
| March 2025 | 72,445 |
| February 2025 | 80,186 |
| January 2025 | 78,133 |
| December 2024 | 90,805 |
| November 2024 | 91,002 |
| October 2024 | 103,366 |
| September 2024 | 59,941 |
| August 2024 | 72,956 |
| July 2024 | 63,585 |
| June 2024 | 69,794 |
| May 2024 | 68,956 |
| April 2024 | 118,311 |
| March 2024 | 110,433 |
| February 2024 | 105,804 |
| January 2024 | 71,229 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Thunder Ranch Wind Project plant, and when do they retire?
1 operable generator totals 298 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 298 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| WT1 | Operating | Onshore Wind Turbine | 298 | 2017 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Thunder Ranch Wind Project plant?
EIA lists no joint owners for Thunder Ranch Wind Project. Thunder Ranch Wind Project, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Thunder Ranch Wind Project plant?
Thunder Ranch Wind Project is in Marland, Noble County, Oklahoma, at 36.5220° N, 97.1450° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Oklahoma are similar in size?
Oklahoma has 69 operable wind plants with 13,344 MW of capacity, and Thunder Ranch Wind Project's 298 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Red Dirt Wind Project | Kingfisher | 299 | 777,648 |
| Kay Wind, LLC | Kay | 299 | 799,243 |
| Kingfisher Wind LLC | Kingfisher | 298 | 956,401 |
| Thunder Ranch Wind Project | Noble | 298 | 805,226 |
| Canadian Hills Wind | Canadian | 294 | 446,009 |
| Maverick Wind Project, LLC | Major | 288 | 855,476 |
| 25 Mile Creek | Ellis | 250 | 1,062,225 |
Source: EIA Forms EIA-860 and EIA-923, 2025.