Adobe Solar is a 20 MW solar power plant in KERN County, California, operated by Southern Power Co, and it generated 36,429 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 31st percentile of U.S. solar plants. By 2025 generation it ranks 4,487th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Adobe Solar plant run compared with other solar plants?
The Adobe Solar plant had a capacity factor of 21% in 2025 on 20 MW of net summer capacity, the 31st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 76 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Adobe Solar | 21% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Adobe Solar plant generating more or less than last year?
Generation at Adobe Solar fell 8.1% from 2024 to 2025, from 39,619 MWh to 36,429 MWh.
| Period | MWh |
|---|---|
| 2024 | 39,619 |
| 2025 | 36,429 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 965 |
| November 2025 | 2,036 |
| October 2025 | 3,363 |
| September 2025 | 2,833 |
| August 2025 | 2,394 |
| July 2025 | 4,414 |
| June 2025 | 4,865 |
| May 2025 | 5,500 |
| April 2025 | 1,111 |
| March 2025 | 3,794 |
| February 2025 | 2,631 |
| January 2025 | 2,523 |
| December 2024 | 1,564 |
| November 2024 | 1,488 |
| October 2024 | 2,518 |
| September 2024 | 3,680 |
| August 2024 | 4,605 |
| July 2024 | 4,712 |
| June 2024 | 4,996 |
| May 2024 | 4,661 |
| April 2024 | 4,510 |
| March 2024 | 2,558 |
| February 2024 | 2,476 |
| January 2024 | 1,851 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Adobe Solar plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 11 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| FRV3 | Operating | Solar Photovoltaic | 20 | 2014 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Adobe Solar plant?
Adobe Solar LLC is the only joint owner reported for Adobe Solar, with 100.0%. Southern Power Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Adobe Solar plant?
Adobe Solar is in Arvin, KERN County, California, at 35.1028° N, 118.9544° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Adobe Solar's 20 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Stroud Solar Station | Fresno | 20 | 14,874 |
| Cantua Solar Station | Fresno | 20 | 23,012 |
| Huron Solar Station | Fresno | 20 | 28,084 |
| Adobe Solar | KERN | 20 | 36,429 |
| Guernsey Solar Station | Kings | 20 | 21,527 |
| Gates Solar Station | Fresno | 20 | 30,509 |
| Alpaugh North | Tulare | 20 | 21,051 |
Source: EIA Forms EIA-860 and EIA-923, 2025.