Bladen Solar power plant, North Carolina

Bladen Solar is a 50 MW solar power plant in Bladen County, North Carolina, operated by Cypress Creek Renewables, and it generated 103,283 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in North Carolina, and its capacity factor sits at the 54th percentile of U.S. solar plants. By 2025 generation it ranks 3,358th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

50 MWNameplate capacity
24%Capacity factor, 2025, 54th percentile, on 50 MW net summer
0.1%Of NC generation, 2025
8 yearsAverage generator age, by MW

How hard does the Bladen Solar plant run compared with other solar plants?

The Bladen Solar plant had a capacity factor of 24% in 2025 on 50 MW of net summer capacity, the 54th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 86 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Bladen Solar24%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Bladen Solar plant generating more or less than last year?

Generation at Bladen Solar fell 0.7% from 2024 to 2025, from 104,030 MWh to 103,283 MWh. Through August 2026 it is running 1.6% behind the same months of 2025.

Net generation by period
PeriodMWh
2024104,030
2025103,283
2026 through August71,811
2025, same months72,989
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20269,253
July 20269,851
June 202610,195
May 202610,253
April 202610,248
March 20269,741
February 20265,547
January 20266,723
December 20255,867
November 20258,092
October 20257,727
September 20258,608
August 20258,837
July 202510,269
June 202510,264
May 20259,563
April 202510,594
March 20259,441
February 20256,744
January 20257,277
December 20246,740
November 20246,905
October 20249,830
September 20248,231
August 20249,883
July 20249,535
June 202410,747
May 202410,156
April 20249,576
March 20249,088
February 20246,367
January 20246,972

Source: EIA Form EIA-923, through August 2026.

How much of North Carolina's electricity comes from the Bladen Solar plant?

Bladen Solar made 0.1% of the 134,194,434 MWh reported by North Carolina plants in 2025, from 0.1% of the state's 39,933 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 80th largest of 928 plants in North Carolina, the 3,754th largest of 14,327 in the U.S. and the 880th largest of 7,223 solar plants. By 2025 generation it is the 70th largest of 872 generating plants in the state.

Bladen Solar within North Carolina, 2025
MeasureThis plantNorth CarolinaShare
Capacity (MW)5039,9330.1%
Generation (MWh)103,283134,194,4340.1%
Solar capacity (MW)507,0250.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Bladen Solar plant, and when do they retire?

1 operable generator totals 50 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s150100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingSolar Photovoltaic502017n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Bladen Solar plant?

EIA lists no joint owners for Bladen Solar. Cypress Creek Renewables operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Bladen Solar plant?

Bladen Solar is in Fayetteville, Bladen County, North Carolina, at 34.8235° N, 78.6235° W. It sits in the Duke Energy Progress East balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in North Carolina are similar in size?

North Carolina has 757 operable solar plants with 7,025 MW of capacity, and Bladen Solar's 50 MW is 1% of that.

Solar plants in North Carolina around this size
PlantCountyMW2025 MWh
Fox Creek SolarFranklin5084,988
Innovative Solar 54Lenoir5098,253
Bullock Solar, LLCVance50101,222
Bladen SolarBladen50103,283
Broad River Solar, LLCCleveland50105,901
Lick Creek Solar, LLCStokes50109,532
Partin SolarSurry5085,551