Solar power plant, North Carolina
Partin Solar power plant, North Carolina
Partin Solar is a 50 MW solar power plant in Surry County, North Carolina, operated by Partin Solar, LLC, and it generated 85,551 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in North Carolina, and its capacity factor sits at the 23rd percentile of U.S. solar plants. By 2025 generation it ranks 3,576th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Partin Solar plant run compared with other solar plants?
The Partin Solar plant had a capacity factor of 20% in 2025 on 50 MW of net summer capacity, the 23rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 71 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Partin Solar | 20% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Partin Solar plant generating more or less than last year?
Generation at Partin Solar rose 49.5% from 2024 to 2025, from 57,241 MWh to 85,551 MWh. Through August 2026 it is running 7.2% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 57,241 |
| 2025 | 85,551 |
| 2026 through August | 67,983 |
| 2025, same months | 63,446 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 10,481 |
| July 2026 | 10,519 |
| June 2026 | 11,495 |
| May 2026 | 8,576 |
| April 2026 | 7,187 |
| March 2026 | 8,844 |
| February 2026 | 6,102 |
| January 2026 | 4,779 |
| December 2025 | 4,797 |
| November 2025 | 6,353 |
| October 2025 | 7,928 |
| September 2025 | 3,027 |
| August 2025 | 8,430 |
| July 2025 | 10,586 |
| June 2025 | 11,444 |
| May 2025 | 7,542 |
| April 2025 | 5,856 |
| March 2025 | 8,739 |
| February 2025 | 5,075 |
| January 2025 | 5,774 |
| December 2024 | 3,748 |
| November 2024 | 4,738 |
| October 2024 | 8,263 |
| September 2024 | 6,552 |
| August 2024 | 8,016 |
| July 2024 | 755 |
| June 2024 | 1,528 |
| May 2024 | 9,003 |
| April 2024 | 9,500 |
| March 2024 | 3,035 |
| February 2024 | 422 |
| January 2024 | 1,681 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Partin Solar plant, and when do they retire?
1 operable generator totals 50 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 50 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 95 | Operating | Solar Photovoltaic | 50 | 2023 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Partin Solar plant?
EIA lists no joint owners for Partin Solar. Partin Solar, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Partin Solar plant?
Partin Solar is in Elkin, Surry County, North Carolina, at 36.2680° N, 80.8219° W. It sits in the Duke Energy Carolinas balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in North Carolina are similar in size?
North Carolina has 757 operable solar plants with 7,025 MW of capacity, and Partin Solar's 50 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Bladen Solar | Bladen | 50 | 103,283 |
| Broad River Solar, LLC | Cleveland | 50 | 105,901 |
| Lick Creek Solar, LLC | Stokes | 50 | 109,532 |
| Partin Solar | Surry | 50 | 85,551 |
| Stanly Solar, LLC | Stanly | 50 | 89,368 |
| Highest Power Solar, LLC | Franklin | 49 | 90,015 |
| Eden Solar LLC | Richmond | 48 | 79,890 |
Source: EIA Forms EIA-860 and EIA-923, 2025.