Blue Canyon Windpower II wind power plant, Oklahoma

Blue Canyon Windpower II is a 151 MW wind power plant in Comanche County, Oklahoma, operated by Blue Canyon Windpower II LLC, and it generated 565,683 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in Oklahoma, and its capacity factor sits at the 84th percentile of U.S. wind plants. By 2025 generation it ranks 1,198th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

151 MWNameplate capacity
43%Capacity factor, 2025, 84th percentile, on 151 MW net summer
0.6%Of OK generation, 2025
20 yearsAverage generator age, by MW

How hard does the Blue Canyon Windpower II plant run compared with other wind plants?

The Blue Canyon Windpower II plant had a capacity factor of 43% in 2025 on 151 MW of net summer capacity, the 84th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 156 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Blue Canyon Windpower II43%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Blue Canyon Windpower II plant generating more or less than last year?

Generation at Blue Canyon Windpower II rose 4.2% from 2024 to 2025, from 543,123 MWh to 565,683 MWh.

Net generation by period
PeriodMWh
2024543,123
2025565,683
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202562,926
November 202554,889
October 202553,033
September 202539,148
August 202534,351
July 202550,588
June 202549,798
May 202537,292
April 202548,862
March 202548,786
February 202542,301
January 202543,709
December 202428,871
November 202437,894
October 202448,328
September 202432,797
August 202448,506
July 202446,705
June 202453,306
May 202437,632
April 202453,628
March 202454,976
February 202459,970
January 202440,510

Source: EIA Form EIA-923, through August 2026.

How much of Oklahoma's electricity comes from the Blue Canyon Windpower II plant?

Blue Canyon Windpower II made 0.6% of the 89,758,877 MWh reported by Oklahoma plants in 2025, from 0.4% of the state's 35,828 MW of capacity. Its share of output is 1.5 times its share of capacity. By capacity it is the 60th largest of 143 plants in Oklahoma, the 1,957th largest of 14,327 in the U.S. and the 434th largest of 1,358 wind plants. By 2025 generation it is the 42nd largest of 135 generating plants in the state.

Blue Canyon Windpower II within Oklahoma, 2025
MeasureThis plantOklahomaShare
Capacity (MW)15135,8280.4%
Generation (MWh)565,68389,758,8770.6%
Wind capacity (MW)15113,3441.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Blue Canyon Windpower II plant, and when do they retire?

1 operable generator totals 151 MW, with an average age of 20 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s1151100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
EW2OperatingOnshore Wind Turbine1512005n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Blue Canyon Windpower II plant?

EIA lists no joint owners for Blue Canyon Windpower II. Blue Canyon Windpower II LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Blue Canyon Windpower II plant?

Blue Canyon Windpower II is in Carnegie, Comanche County, Oklahoma, at 34.8661° N, 98.6056° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Oklahoma are similar in size?

Oklahoma has 69 operable wind plants with 13,344 MW of capacity, and Blue Canyon Windpower II's 151 MW is 1% of that.

Wind plants in Oklahoma around this size
PlantCountyMW2025 MWh
Rock Falls Wind Farm LLCKay155374,311
Keenan II Renewable Energy Co LLCWoodward152246,635
Grant Wind, LLCGrant152496,264
Blue Canyon Windpower IIComanche151565,683
Osage Wind, LLCOsage150480,273
Origin WindMurray150295,728
Rocky Ridge Wind ProjectKiowa149321,675

Source: EIA Forms EIA-860 and EIA-923, 2025.