Skip to main content
RateWatt

Hydro power plant, Georgia

Blue Ridge hydroelectric power plant, Georgia

Blue Ridge is a 23.5 MW hydro power plant in Fannin County, Georgia, operated by Tennessee Valley Authority, and it generated 23,581 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 11th percentile of U.S. hydro plants. By 2025 generation it ranks 5,039th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

23.5 MWNameplate capacity
16%Capacity factor, 2025, 11th percentile, on 17.3 MW net summer
5,039thU.S. rank by generation, 2025
90 yearsAverage generator age, by MW

How hard does the Blue Ridge plant run compared with other hydro plants?

The Blue Ridge plant had a capacity factor of 16% in 2025 on 17.3 MW of net summer capacity, the 11th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 57 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Blue Ridge16%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Blue Ridge plant generating more or less than last year?

Generation at Blue Ridge fell 8.0% from 2024 to 2025, from 25,631 MWh to 23,581 MWh.

Net generation by period
PeriodMWh
202425,631
202523,581
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20251,572
November 2025732
October 2025570
September 20252,034
August 20253,481
July 20251,771
June 20252,673
May 20253,909
April 20252,389
March 2025189
February 20252,059
January 20252,202
December 20241,673
November 2024324
October 20242,182
September 20241,797
August 20241,976
July 20241,733
June 20242,489
May 20243,090
April 20241,092
March 20242,750
February 20242,908
January 20243,617

Source: EIA Form EIA-923, through August 2026.

How much of Georgia's electricity comes from the Blue Ridge plant?

Blue Ridge made 0.0% of the 144,967,352 MWh reported by Georgia plants in 2025, from 0.1% of the state's 42,719 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 116th largest of 263 plants in Georgia, the 4,629th largest of 14,327 in the U.S. and the 411th largest of 1,393 hydro plants. By 2025 generation it is the 133rd largest of 242 generating plants in the state.

Blue Ridge within Georgia, 2025
MeasureThis plantGeorgiaShare
Capacity (MW)2442,7190.1%
Generation (MWh)23,581144,967,3520.0%
Hydro capacity (MW)241,5501.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Blue Ridge plant, and when do they retire?

2 operable generators total 23.5 MW, with an average age of 90 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1930s12294%none reported
1990s126%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric221931n/a
2OperatingConventional Hydroelectric21994n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Blue Ridge plant?

EIA lists no joint owners for Blue Ridge. Tennessee Valley Authority operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Blue Ridge plant?

Blue Ridge is in Blue Ridge, Fannin County, Georgia, at 34.8839° N, 84.2822° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Georgia are similar in size?

Georgia has 27 operable hydro plants with 1,550 MW of capacity, and Blue Ridge's 23.5 MW is 2% of that.

Hydro plants in Georgia around this size
PlantCountyMW2025 MWh
Sinclair DamBaldwin45104,972
TugaloHabersham4593,858
North HighlandsMuscogee3096,941
Blue RidgeFannin2423,581
YonahStephens2335,371
Stevens CreekColumbia1866,150
Lake Blackshear ProjectWorth1734,556

Source: EIA Forms EIA-860 and EIA-923, 2025.