Hydro power plant, Georgia

North Highlands hydroelectric power plant, Georgia

North Highlands is a 29.6 MW hydro power plant in Muscogee County, Georgia, operated by Georgia Power Co, and it generated 96,941 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Georgia, and its capacity factor sits at the 48th percentile of U.S. hydro plants. By 2025 generation it ranks 3,433rd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

29.6 MWNameplate capacity
32%Capacity factor, 2025, 48th percentile, on 34.4 MW net summer
0.1%Of GA generation, 2025
62 yearsAverage generator age, by MW

How hard does the North Highlands plant run compared with other hydro plants?

The North Highlands plant had a capacity factor of 32% in 2025 on 34.4 MW of net summer capacity, the 48th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 117 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
North Highlands32%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the North Highlands plant generating more or less than last year?

Generation at North Highlands rose 3.1% from 2024 to 2025, from 94,037 MWh to 96,941 MWh.

Net generation by period
PeriodMWh
202494,037
202596,941
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20252,989
November 20254,093
October 20254,834
September 20256,934
August 20259,790
July 20258,672
June 202510,040
May 202512,153
April 202511,438
March 202510,117
February 20259,201
January 20256,680
December 20247,317
November 20245,553
October 20244,774
September 20249,275
August 20247,123
July 20247,284
June 20244,193
May 20247,634
April 20248,319
March 202412,344
February 20249,260
January 202410,961

Source: EIA Form EIA-923, through August 2026.

How much of Georgia's electricity comes from the North Highlands plant?

North Highlands made 0.1% of the 144,967,352 MWh reported by Georgia plants in 2025, from 0.1% of the state's 42,719 MW of capacity. By capacity it is the 114th largest of 263 plants in Georgia, the 4,420th largest of 14,327 in the U.S. and the 374th largest of 1,393 hydro plants. By 2025 generation it is the 85th largest of 242 generating plants in the state.

North Highlands within Georgia, 2025
MeasureThis plantGeorgiaShare
Capacity (MW)3042,7190.1%
Generation (MWh)96,941144,967,3520.1%
Hydro capacity (MW)301,5501.9%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the North Highlands plant, and when do they retire?

4 operable generators total 29.6 MW, with an average age of 62 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1960s430100%none reported
Every generator, 4 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric91963n/a
2OperatingConventional Hydroelectric91963n/a
3OperatingConventional Hydroelectric91963n/a
4OperatingConventional Hydroelectric21963n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the North Highlands plant?

EIA lists no joint owners for North Highlands. Georgia Power Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Georgia Power Co charge homes?

Georgia Power Co, the operator of North Highlands, had an average residential price of 16.28¢ per kWh and an average bill of $161 a month in 2025, 10% above the Georgia average of 14.74¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Georgia
Georgia Power Co16.28¢$16110% higher
Georgia average14.74¢$159
U.S. average17.23¢$15117% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the North Highlands plant?

North Highlands is in Columbus, Muscogee County, Georgia, at 32.4994° N, 84.9965° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Georgia are similar in size?

Georgia has 27 operable hydro plants with 1,550 MW of capacity, and North Highlands' 29.6 MW is 2% of that.

Hydro plants in Georgia around this size
PlantCountyMW2025 MWh
Sinclair DamBaldwin45104,972
TugaloHabersham4593,858
North HighlandsMuscogee3096,941
Blue RidgeFannin2423,581
YonahStephens2335,371
Stevens CreekColumbia1866,150

Source: EIA Forms EIA-860 and EIA-923, 2025.