Wind power plant, Missouri
Bluegrass Ridge wind power plant, Missouri
Bluegrass Ridge is a 56.7 MW wind power plant in Gentry County, Missouri, operated by Wind Capital Holdings, LLC, and it generated 197,446 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Missouri, and its capacity factor sits at the 72nd percentile of U.S. wind plants. By 2025 generation it ranks 2,512th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Bluegrass Ridge plant run compared with other wind plants?
The Bluegrass Ridge plant had a capacity factor of 40% in 2025 on 56.7 MW of net summer capacity, the 72nd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 145 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Bluegrass Ridge | 40% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Bluegrass Ridge plant generating more or less than last year?
Bluegrass Ridge generated 197,446 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 2.2% ahead of the same months of 2025. 2024 has output for only 9 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 82,273 |
| 2025 | 197,446 |
| 2026 through August | 135,256 |
| 2025, same months | 132,356 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 11,391 |
| July 2026 | 8,543 |
| June 2026 | 13,075 |
| May 2026 | 15,115 |
| April 2026 | 24,582 |
| March 2026 | 24,840 |
| February 2026 | 17,311 |
| January 2026 | 20,399 |
| December 2025 | 20,581 |
| November 2025 | 18,301 |
| October 2025 | 17,419 |
| September 2025 | 8,789 |
| August 2025 | 9,098 |
| July 2025 | 10,276 |
| June 2025 | 12,981 |
| May 2025 | 14,045 |
| April 2025 | 20,848 |
| March 2025 | 24,855 |
| February 2025 | 19,051 |
| January 2025 | 21,202 |
| December 2024 | 17,895 |
| November 2024 | 14,786 |
| October 2024 | 5,950 |
| September 2024 | 0 |
| August 2024 | 0 |
| July 2024 | 0 |
| June 2024 | 1,425 |
| May 2024 | 3,748 |
| April 2024 | 11,503 |
| March 2024 | 11,341 |
| February 2024 | 8,919 |
| January 2024 | 6,706 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Bluegrass Ridge plant, and when do they retire?
1 operable generator totals 56.7 MW, with an average age of 18 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 57 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 57 | 2007 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Bluegrass Ridge plant?
EIA lists no joint owners for Bluegrass Ridge. Wind Capital Holdings, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Bluegrass Ridge plant?
Bluegrass Ridge is in King City, Gentry County, Missouri, at 40.1006° N, 94.4869° W. It sits in the Associated Electric Cooperative, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Missouri are similar in size?
Missouri has 14 operable wind plants with 2,454 MW of capacity, and Bluegrass Ridge's 56.7 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Bluegrass Ridge | Gentry | 57 | 197,446 |
| Cow Branch | Atchison | 50 | 145,037 |
| Conception | Nodaway | 50 | 182,280 |
Source: EIA Forms EIA-860 and EIA-923, 2025.