Wind power plant, Missouri
Conception wind power plant, Missouri
Conception is a 50.4 MW wind power plant in Nodaway County, Missouri, operated by CR Clearing, LLC, and it generated 182,280 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Missouri, and its capacity factor sits at the 78th percentile of U.S. wind plants. By 2025 generation it ranks 2,621st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Conception plant run compared with other wind plants?
The Conception plant had a capacity factor of 41% in 2025 on 50.4 MW of net summer capacity, the 78th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 151 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Conception | 41% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Conception plant generating more or less than last year?
Generation at Conception rose 68.6% from 2024 to 2025, from 108,114 MWh to 182,280 MWh. Through August 2026 it is running 0.7% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 108,114 |
| 2025 | 182,280 |
| 2026 through August | 121,479 |
| 2025, same months | 122,377 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 8,905 |
| July 2026 | 7,889 |
| June 2026 | 12,789 |
| May 2026 | 13,894 |
| April 2026 | 22,116 |
| March 2026 | 21,687 |
| February 2026 | 15,642 |
| January 2026 | 18,557 |
| December 2025 | 17,925 |
| November 2025 | 16,168 |
| October 2025 | 16,483 |
| September 2025 | 9,327 |
| August 2025 | 8,717 |
| July 2025 | 9,907 |
| June 2025 | 12,145 |
| May 2025 | 12,448 |
| April 2025 | 19,748 |
| March 2025 | 22,297 |
| February 2025 | 17,926 |
| January 2025 | 19,189 |
| December 2024 | 16,265 |
| November 2024 | 15,315 |
| October 2024 | 19,379 |
| September 2024 | 13,138 |
| August 2024 | 8,702 |
| July 2024 | 3,352 |
| June 2024 | 106 |
| May 2024 | 950 |
| April 2024 | 5,188 |
| March 2024 | 8,823 |
| February 2024 | 9,744 |
| January 2024 | 7,152 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Conception plant, and when do they retire?
1 operable generator totals 50.4 MW, with an average age of 17 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 50 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 50 | 2008 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Conception plant?
EIA lists no joint owners for Conception. CR Clearing, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Conception plant?
Conception is in Stanberry, Nodaway County, Missouri, at 40.2572° N, 94.6722° W. It sits in the Associated Electric Cooperative, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Missouri are similar in size?
Missouri has 14 operable wind plants with 2,454 MW of capacity, and Conception's 50.4 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Bluegrass Ridge | Gentry | 57 | 197,446 |
| Cow Branch | Atchison | 50 | 145,037 |
| Conception | Nodaway | 50 | 182,280 |
Source: EIA Forms EIA-860 and EIA-923, 2025.