Wind power plant, Nebraska
Broken Bow Wind II, LLC power plant, Nebraska
Broken Bow Wind II, LLC is a 73.1 MW wind power plant in Custer County, Nebraska, operated by RWE Clean Energy, and it generated 239,638 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in Nebraska, and its capacity factor sits at the 65th percentile of U.S. wind plants. By 2025 generation it ranks 2,275th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Broken Bow Wind II, LLC plant run compared with other wind plants?
The Broken Bow Wind II, LLC plant had a capacity factor of 37% in 2025 on 73.1 MW of net summer capacity, the 65th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 137 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Broken Bow Wind II, LLC | 37% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Broken Bow Wind II, LLC plant generating more or less than last year?
Generation at Broken Bow Wind II, LLC fell 5.5% from 2024 to 2025, from 253,599 MWh to 239,638 MWh.
| Period | MWh |
|---|---|
| 2024 | 253,599 |
| 2025 | 239,638 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 28,939 |
| November 2025 | 20,300 |
| October 2025 | 15,797 |
| September 2025 | 17,215 |
| August 2025 | 18,949 |
| July 2025 | 21,104 |
| June 2025 | 18,476 |
| May 2025 | 21,869 |
| April 2025 | 17,933 |
| March 2025 | 18,510 |
| February 2025 | 17,825 |
| January 2025 | 22,721 |
| December 2024 | 19,242 |
| November 2024 | 14,137 |
| October 2024 | 12,929 |
| September 2024 | 27,644 |
| August 2024 | 16,711 |
| July 2024 | 16,482 |
| June 2024 | 21,787 |
| May 2024 | 22,654 |
| April 2024 | 30,466 |
| March 2024 | 27,058 |
| February 2024 | 23,321 |
| January 2024 | 21,168 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Broken Bow Wind II, LLC plant, and when do they retire?
1 operable generator totals 73.1 MW, with an average age of 11 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 73 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| BBII | Operating | Onshore Wind Turbine | 73 | 2014 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Broken Bow Wind II, LLC plant?
EIA lists no joint owners for Broken Bow Wind II, LLC. RWE Clean Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Broken Bow Wind II, LLC plant?
Broken Bow Wind II, LLC is in Broken Bow, Custer County, Nebraska, at 41.3239° N, 99.3231° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Nebraska are similar in size?
Nebraska has 33 operable wind plants with 3,527 MW of capacity, and Broken Bow Wind II, LLC's 73.1 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Broken Bow Wind LLC | Custer | 80 | 221,654 |
| Steele Flats Wind Project LLC | Jefferson | 79 | 332,567 |
| Prairie Breeze II | Antelope | 73 | 267,691 |
| Broken Bow Wind II, LLC | Custer | 73 | 239,638 |
| Flat Water Wind Farm LLC | Richardson | 60 | 203,879 |
| Ainsworth Wind | Brown | 59 | 66,389 |
| TPW Petersburg | Boone | 41 | 155,277 |
Source: EIA Forms EIA-860 and EIA-923, 2025.