Wind power plant, Nebraska
TPW Petersburg wind power plant, Nebraska
TPW Petersburg is a 40.5 MW wind power plant in Boone County, Nebraska, operated by TPW Petersburg LLC, and it generated 155,277 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Nebraska, and its capacity factor sits at the 87th percentile of U.S. wind plants. By 2025 generation it ranks 2,850th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the TPW Petersburg plant run compared with other wind plants?
The TPW Petersburg plant had a capacity factor of 44% in 2025 on 40.5 MW of net summer capacity, the 87th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 160 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| TPW Petersburg | 44% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the TPW Petersburg plant generating more or less than last year?
Generation at TPW Petersburg fell 4.4% from 2024 to 2025, from 162,392 MWh to 155,277 MWh.
| Period | MWh |
|---|---|
| 2024 | 162,392 |
| 2025 | 155,277 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 14,304 |
| November 2025 | 12,868 |
| October 2025 | 14,199 |
| September 2025 | 9,808 |
| August 2025 | 8,816 |
| July 2025 | 9,219 |
| June 2025 | 10,861 |
| May 2025 | 11,154 |
| April 2025 | 17,189 |
| March 2025 | 17,359 |
| February 2025 | 13,604 |
| January 2025 | 15,896 |
| December 2024 | 14,244 |
| November 2024 | 14,596 |
| October 2024 | 16,719 |
| September 2024 | 14,631 |
| August 2024 | 8,713 |
| July 2024 | 7,665 |
| June 2024 | 12,270 |
| May 2024 | 14,877 |
| April 2024 | 15,503 |
| March 2024 | 17,800 |
| February 2024 | 13,430 |
| January 2024 | 11,944 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the TPW Petersburg plant, and when do they retire?
1 operable generator totals 40.5 MW, with an average age of 14 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 41 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| PETE | Operating | Onshore Wind Turbine | 41 | 2011 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the TPW Petersburg plant?
EIA lists no joint owners for TPW Petersburg. TPW Petersburg LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the TPW Petersburg plant?
TPW Petersburg is in Petersburg, Boone County, Nebraska, at 41.8646° N, 97.9612° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Nebraska are similar in size?
Nebraska has 33 operable wind plants with 3,527 MW of capacity, and TPW Petersburg's 40.5 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Broken Bow Wind II, LLC | Custer | 73 | 239,638 |
| Flat Water Wind Farm LLC | Richardson | 60 | 203,879 |
| Ainsworth Wind | Brown | 59 | 66,389 |
| TPW Petersburg | Boone | 41 | 155,277 |
| Crofton Bluffs Wind LLC | Knox | 40 | 107,958 |
| Prairie Breeze III | Antelope | 36 | 135,251 |
| Kimball Wind | Kimball | 30 | 124,468 |
Source: EIA Forms EIA-860 and EIA-923, 2025.