Cavalry Solar Hybrid is a 245 MW power plant, 200 MW of it solar, in White County, Indiana, operated by Cavalry Energy Center LLC, and it generated 373,570 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Indiana, and its capacity factor sits at the 41st percentile of U.S. solar plants. By 2025 generation it ranks 1,686th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

245 MWNameplate capacity
22%Capacity factor, 2025, solar units, 41st percentile, on 200 MW net summer
0.3%Of IN generation, 2025
1 yearAverage generator age, by MW

How hard does the Cavalry Solar Hybrid plant run compared with other solar plants?

The Cavalry Solar Hybrid plant's solar units had a capacity factor of 22% in 2025 on 200 MW of net summer capacity, the 41st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 80 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Cavalry Solar Hybrid22%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its solar generators only. Values above 105% are left out of the comparison.

Is the Cavalry Solar Hybrid plant generating more or less than last year?

Cavalry Solar Hybrid generated 373,570 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 4.9% behind the same months of 2025. 2024 has output for only 8 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024262,430
2025373,570
2026 through August267,499
2025, same months281,239
Monthly generation, May 2024 to Aug 2026
MonthMWh
August 202637,266
July 202646,841
June 202642,564
May 202646,969
April 202634,532
March 202626,534
February 202618,018
January 202614,775
December 202510,359
November 202514,596
October 202528,919
September 202538,457
August 202544,001
July 202540,929
June 202541,830
May 202544,815
April 202536,698
March 202532,507
February 202521,288
January 202519,171
December 202410,509
November 202411,645
October 202429,747
September 202435,846
August 202447,076
July 202447,769
June 202444,603
May 202435,235

Source: EIA Form EIA-923, through August 2026.

How much of Indiana's electricity comes from the Cavalry Solar Hybrid plant?

Cavalry Solar Hybrid made 0.3% of the 106,870,299 MWh reported by Indiana plants in 2025, from 0.7% of the state's 33,631 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 31st largest of 221 plants in Indiana, the 1,298th largest of 14,327 in the U.S. and the 180th largest of 7,223 solar plants on its solar units alone. By 2025 generation it is the 43rd largest of 207 generating plants in the state.

Cavalry Solar Hybrid within Indiana, 2025
MeasureThis plantIndianaShare
Capacity (MW)24533,6310.7%
Generation (MWh)373,570106,870,2990.3%
Solar capacity (MW)2004,5914.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Cavalry Solar Hybrid plant, and when do they retire?

2 operable generators total 245 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s2245100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CAVBSOperatingBatteries452024n/a
CAVPVOperatingSolar Photovoltaic2002024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Cavalry Solar Hybrid plant?

EIA lists no joint owners for Cavalry Solar Hybrid. Cavalry Energy Center LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What fuels does the Cavalry Solar Hybrid plant use?

Cavalry Solar Hybrid has capacity on 2 fuels: 82% solar and 18% battery and pumped storage. In 2025, solar made 103% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Solar20081.6%386,028
Battery and pumped storage4518.4%-12,458

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Cavalry Solar Hybrid plant?

Cavalry Solar Hybrid is in Monon, White County, Indiana, at 40.8953° N, 86.8102° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region RFC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Indiana are similar in size?

Indiana has 121 operable solar plants with 4,591 MW of capacity, and Cavalry Solar Hybrid's 200 MW is 4% of that.

Solar plants in Indiana around this size
PlantCountyMW2025 MWh
Fairbanks Solar ProjectSullivan250357,949
Riverstart Solar Park LLCRandolph200390,012
Indiana Crossroads Solar ParkWhite200378,938
Cavalry Solar HybridWhite200386,028
Crossroads Solar (IN)Fountain2005,901
Gibson SolarGibson200141,836
Appleseed SolarCass200150,379