Natural gas power plant, Texas
CFB Power Plant, Texas
CFB Power Plant is a 310 MW natural gas power plant in Calhoun County, Texas, operated by Formosa Plastics Corp, and it generated 851,532 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 60th percentile of U.S. natural gas plants. By 2025 generation it ranks 833rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does CFB Power Plant run compared with other natural gas plants?
CFB Power Plant had a capacity factor of 34% in 2025 on 286 MW of net summer capacity, the 60th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 124 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| CFB Power Plant | 34% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is CFB Power Plant generating more or less than last year?
Generation at CFB Power Plant fell 0.2% from 2024 to 2025, from 853,601 MWh to 851,532 MWh.
| Period | MWh |
|---|---|
| 2024 | 853,601 |
| 2025 | 851,532 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 57,636 |
| November 2025 | 77,201 |
| October 2025 | 100,889 |
| September 2025 | 87,881 |
| August 2025 | 113,295 |
| July 2025 | 103,998 |
| June 2025 | 102,810 |
| May 2025 | 54,385 |
| April 2025 | 42,651 |
| March 2025 | 33,498 |
| February 2025 | 39,034 |
| January 2025 | 38,254 |
| December 2024 | 40,818 |
| November 2024 | 38,494 |
| October 2024 | 38,661 |
| September 2024 | 75,150 |
| August 2024 | 74,317 |
| July 2024 | 79,382 |
| June 2024 | 94,039 |
| May 2024 | 87,704 |
| April 2024 | 77,979 |
| March 2024 | 117,832 |
| February 2024 | 82,858 |
| January 2024 | 46,367 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at CFB Power Plant, and when do they retire?
2 operable generators total 310 MW, with an average age of 13 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 2 | 310 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| G2101 | Operating | Natural Gas Steam Turbine | 155 | 2012 | n/a |
| G2201 | Operating | Natural Gas Steam Turbine | 155 | 2012 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns CFB Power Plant?
EIA lists no joint owners for CFB Power Plant. Formosa Plastics Corp operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is CFB Power Plant?
CFB Power Plant is in Point Comfort, Calhoun County, Texas, at 28.6503° N, 96.5397° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Texas are similar in size?
Texas has 305 operable natural gas plants with 81,574 MW of capacity, and CFB Power Plant's 310 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| DeCordova Steam Electric Station | Hood | 358 | 63,812 |
| Knox Lee | Gregg | 351 | 546,128 |
| Bayou Cogen Plant | Harris | 318 | 2,155,869 |
| CFB Power Plant | Calhoun | 310 | 851,532 |
| Johnson County | Johnson | 283 | 1,264,776 |
| Paris Energy Center | Lamar | 266 | 320,433 |
| Laredo | Webb | 264 | 24,064 |
Source: EIA Forms EIA-860 and EIA-923, 2025.