Natural gas power plant, Texas
Chickadee G-3 natural gas power plant, Texas
Chickadee G-3 is a 34.8 MW natural gas power plant in Jefferson County, Texas, operated by Chickadee 3-G Purchaser LLC, and it generated 259,225 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 98th percentile of U.S. natural gas plants. By 2025 generation it ranks 2,166th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Chickadee G-3 plant run compared with other natural gas plants?
The Chickadee G-3 plant had a capacity factor of 91% in 2025 on 32 MW of net summer capacity, the 98th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 332 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Chickadee G-3 | 91% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Chickadee G-3 plant generating more or less than last year?
Generation at Chickadee G-3 fell 6.0% from 2024 to 2025, from 275,649 MWh to 259,225 MWh. Through August 2026 it is running 29.4% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 275,649 |
| 2025 | 259,225 |
| 2026 through August | 129,916 |
| 2025, same months | 184,005 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 10,438 |
| July 2026 | 14,712 |
| June 2026 | 15,493 |
| May 2026 | 15,873 |
| April 2026 | 16,355 |
| March 2026 | 17,127 |
| February 2026 | 19,082 |
| January 2026 | 20,836 |
| December 2025 | 19,284 |
| November 2025 | 19,444 |
| October 2025 | 18,151 |
| September 2025 | 18,341 |
| August 2025 | 21,342 |
| July 2025 | 21,837 |
| June 2025 | 23,622 |
| May 2025 | 24,223 |
| April 2025 | 23,477 |
| March 2025 | 22,036 |
| February 2025 | 22,821 |
| January 2025 | 24,647 |
| December 2024 | 24,634 |
| November 2024 | 23,010 |
| October 2024 | 20,866 |
| September 2024 | 21,301 |
| August 2024 | 21,610 |
| July 2024 | 22,490 |
| June 2024 | 22,298 |
| May 2024 | 23,313 |
| April 2024 | 23,407 |
| March 2024 | 25,022 |
| February 2024 | 22,776 |
| January 2024 | 24,922 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Chickadee G-3 plant, and when do they retire?
5 operable generators total 34.8 MW, with an average age of 31 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 1 | 15 | 43% | none reported |
| 1990s | 4 | 20 | 57% | none reported |
Every generator, 5 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 3N80 | Operating | Natural Gas Steam Turbine | 15 | 1987 | n/a |
| 2N80 | Operating | Natural Gas Fired Combustion Turbine | 5 | 1999 | n/a |
| N802 | Operating | Natural Gas Fired Combustion Turbine | 5 | 1999 | n/a |
| N803 | Operating | Natural Gas Fired Combustion Turbine | 5 | 1999 | n/a |
| N804 | Operating | Natural Gas Fired Combustion Turbine | 5 | 1999 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Chickadee G-3 plant?
EIA lists no joint owners for Chickadee G-3. Chickadee 3-G Purchaser LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Chickadee G-3 plant?
Chickadee G-3 is in Beaumont, Jefferson County, Texas, at 29.9728° N, 94.2142° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Texas are similar in size?
Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Chickadee G-3's 34.8 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Corpus Christi | Nueces | 41 | 85,583 |
| Port Arthur Texas Refinery | Jefferson | 38 | 177,981 |
| Texas Petrochemicals | Harris | 35 | 205,280 |
| Chickadee G-3 | Jefferson | 35 | 255,119 |
| NEWPP | Harris | 30 | n/a |
| Wasson CO2 Removal Plant | Yoakum | 23 | 114,005 |
| Bryan (TX) | Brazos | 22 | 1,004 |
Source: EIA Forms EIA-860 and EIA-923, 2025.