Wasson CO2 Removal Plant is a 23.4 MW natural gas power plant in Yoakum County, Texas, operated by Occidental Permian Ltd, and it generated 114,005 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 86th percentile of U.S. natural gas plants. By 2025 generation it ranks 3,267th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does Wasson CO2 Removal Plant run compared with other natural gas plants?
Wasson CO2 Removal Plant had a capacity factor of 71% in 2025 on 18.4 MW of net summer capacity, the 86th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 258 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Wasson CO2 Removal Plant | 71% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is Wasson CO2 Removal Plant generating more or less than last year?
Generation at Wasson CO2 Removal Plant fell 21.7% from 2024 to 2025, from 145,598 MWh to 114,005 MWh.
| Period | MWh |
|---|---|
| 2024 | 145,598 |
| 2025 | 114,005 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 8,657 |
| November 2025 | 7,597 |
| October 2025 | 9,628 |
| September 2025 | 11,124 |
| August 2025 | 13,200 |
| July 2025 | 11,923 |
| June 2025 | 10,474 |
| May 2025 | 9,828 |
| April 2025 | 6,828 |
| March 2025 | 6,396 |
| February 2025 | 8,199 |
| January 2025 | 10,152 |
| December 2024 | 10,531 |
| November 2024 | 9,817 |
| October 2024 | 12,253 |
| September 2024 | 14,146 |
| August 2024 | 17,049 |
| July 2024 | 15,088 |
| June 2024 | 13,959 |
| May 2024 | 12,373 |
| April 2024 | 9,260 |
| March 2024 | 9,856 |
| February 2024 | 8,686 |
| January 2024 | 12,580 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at Wasson CO2 Removal Plant, and when do they retire?
1 operable generator totals 23.4 MW, with an average age of 37 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 1 | 23 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Natural Gas Fired Combustion Turbine | 23 | 1988 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns Wasson CO2 Removal Plant?
EIA lists no joint owners for Wasson CO2 Removal Plant. Occidental Permian Ltd operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is Wasson CO2 Removal Plant?
Wasson CO2 Removal Plant is in Denver City, Yoakum County, Texas, at 33.0099° N, 102.7569° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Texas are similar in size?
Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Wasson CO2 Removal Plant's 23.4 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Texas Petrochemicals | Harris | 35 | 205,280 |
| Chickadee G-3 | Jefferson | 35 | 255,119 |
| NEWPP | Harris | 30 | n/a |
| Wasson CO2 Removal Plant | Yoakum | 23 | 114,005 |
| Bryan (TX) | Brazos | 22 | 1,004 |
| Enterprise Products Operating | Chambers | 21 | 150,144 |
| Phelps Dodge Refining | El Paso | 20 | 59,192 |
Source: EIA Forms EIA-860 and EIA-923, 2025.