Chilhowee is a 49.8 MW hydro power plant in Blount County, Tennessee, operated by Brookfield Smoky Mountain Hydropower LP, and it generated 157,680 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Tennessee, and its capacity factor sits at the 55th percentile of U.S. hydro plants. By 2025 generation it ranks 2,825th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Chilhowee plant run compared with other hydro plants?
The Chilhowee plant had a capacity factor of 35% in 2025 on 51 MW of net summer capacity, the 55th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 129 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Chilhowee | 35% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Chilhowee plant generating more or less than last year?
Generation at Chilhowee fell 0.9% from 2024 to 2025, from 159,115 MWh to 157,680 MWh.
| Period | MWh |
|---|---|
| 2024 | 159,115 |
| 2025 | 157,680 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 9,578 |
| November 2025 | 9,578 |
| October 2025 | 13,645 |
| September 2025 | 14,020 |
| August 2025 | 13,098 |
| July 2025 | 10,234 |
| June 2025 | 14,326 |
| May 2025 | 18,394 |
| April 2025 | 8,420 |
| March 2025 | 12,098 |
| February 2025 | 18,281 |
| January 2025 | 16,008 |
| December 2024 | 13,829 |
| November 2024 | 11,013 |
| October 2024 | 17,375 |
| September 2024 | 9,983 |
| August 2024 | 8,914 |
| July 2024 | 8,408 |
| June 2024 | 12,072 |
| May 2024 | 10,853 |
| April 2024 | 5,526 |
| March 2024 | 16,979 |
| February 2024 | 22,251 |
| January 2024 | 21,912 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Chilhowee plant, and when do they retire?
3 operable generators total 49.8 MW, with an average age of 68 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1950s | 3 | 50 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 17 | 1957 | n/a |
| 2 | Operating | Conventional Hydroelectric | 17 | 1957 | n/a |
| 3 | Operating | Conventional Hydroelectric | 17 | 1957 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Chilhowee plant?
EIA lists no joint owners for Chilhowee. Brookfield Smoky Mountain Hydropower LP operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Chilhowee plant?
Chilhowee is in Tallassee, Blount County, Tennessee, at 35.5453° N, 84.0503° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Tennessee are similar in size?
Tennessee has 28 operable hydro plants with 2,520 MW of capacity, and Chilhowee's 49.8 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Fort Patrick Henry | Sullivan | 59 | 94,765 |
| Watauga | Carter | 58 | 94,002 |
| Dale Hollow | Clay | 54 | 120,945 |
| Chilhowee | Blount | 50 | 157,680 |
| Tims Ford | Franklin | 46 | 41,215 |
| South Holston | Sullivan | 39 | 121,520 |
| Cheatham | Dickson | 36 | 191,448 |