DeRidder Mill biomass power plant, Louisiana
DeRidder Mill is a 61.5 MW biomass power plant in Beauregard Parish, Louisiana, operated by Packaging Corporation of America, and it generated 404,514 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Louisiana, and its capacity factor sits at the 71st percentile of U.S. biomass plants. By 2025 generation it ranks 1,577th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the DeRidder Mill plant run compared with other biomass plants?
The DeRidder Mill plant had a capacity factor of 62% in 2025 on 61.5 MW of net summer capacity, the 71st percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 226 days at full output out of 365.
0%Shaded: the middle half of biomass plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| DeRidder Mill | 62% |
| Biomass plants, 75th percentile | 65% |
| Biomass plants, median | 48% |
| Biomass plants, 25th percentile | 35% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the DeRidder Mill plant generating more or less than last year?
Generation at DeRidder Mill rose 0.5% from 2024 to 2025, from 402,395 MWh to 404,514 MWh.
| Period | MWh |
|---|---|
| 2024 | 402,395 |
| 2025 | 404,514 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 36,772 |
| November 2025 | 34,468 |
| October 2025 | 26,424 |
| September 2025 | 32,913 |
| August 2025 | 34,548 |
| July 2025 | 34,323 |
| June 2025 | 33,342 |
| May 2025 | 34,878 |
| April 2025 | 33,787 |
| March 2025 | 35,023 |
| February 2025 | 31,902 |
| January 2025 | 36,134 |
| December 2024 | 35,316 |
| November 2024 | 33,007 |
| October 2024 | 29,974 |
| September 2024 | 32,764 |
| August 2024 | 28,929 |
| July 2024 | 34,040 |
| June 2024 | 33,378 |
| May 2024 | 35,106 |
| April 2024 | 34,249 |
| March 2024 | 35,617 |
| February 2024 | 32,788 |
| January 2024 | 37,224 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the DeRidder Mill plant, and when do they retire?
1 operable generator totals 61.5 MW, with an average age of 56 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1960s | 1 | 62 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| TG | Operating | Wood/Wood Waste Biomass | 62 | 1969 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the DeRidder Mill plant?
EIA lists no joint owners for DeRidder Mill. Packaging Corporation of America operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the DeRidder Mill plant?
DeRidder Mill is in DeRidder, Beauregard Parish, Louisiana, at 30.8606° N, 93.3756° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which biomass plants in Louisiana are similar in size?
Louisiana has 9 operable biomass plants with 487 MW of capacity, and DeRidder Mill's 61.5 MW is 13% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Gaylord Container Bogalusa | Washington | 100 | 420,071 |
| International Paper Red River Mill | Natchitoches | 79 | 73,436 |
| Westrock Hodge (LA) | Jackson | 66 | 315,245 |
| DeRidder Mill | Beauregard | 62 | 333,234 |
| Plant 31 Paper Mill | Ouachita | 45 | 193,354 |
Source: EIA Forms EIA-860 and EIA-923, 2025.