Hydro power plant, Colorado

Flatiron hydroelectric power plant, Colorado

Flatiron is a 94.5 MW power plant, 86 MW of it hydro, in Larimer County, Colorado, operated by U S Bureau of Reclamation, and it generated 214,845 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Colorado, and its capacity factor sits at the 53rd percentile of U.S. hydro plants. By 2025 generation it ranks 2,391st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

94.5 MWNameplate capacity
34%Capacity factor, 2025, hydro units, 53rd percentile, on 86 MW net summer
0.4%Of CO generation, 2025
71 yearsAverage generator age, by MW

How hard does the Flatiron plant run compared with other hydro plants?

The Flatiron plant's hydro units had a capacity factor of 34% in 2025 on 86 MW of net summer capacity, the 53rd percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 126 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Flatiron34%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its hydro generators only. Values above 105% are left out of the comparison.

Is the Flatiron plant generating more or less than last year?

Generation at Flatiron rose 26.8% from 2024 to 2025, from 169,427 MWh to 214,845 MWh. Through August 2026 it is running 5.2% behind the same months of 2025.

Net generation by period
PeriodMWh
2024169,427
2025214,845
2026 through August133,845
2025, same months141,204
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202620,888
July 202620,396
June 202619,078
May 202621,712
April 20262,550
March 20265,371
February 202621,430
January 202622,420
December 202523,102
November 202519,533
October 20257,481
September 202523,525
August 202522,453
July 202519,154
June 202524,911
May 202516,458
April 2025549
March 202516,203
February 202520,329
January 202521,147
December 202424,109
November 20249,544
October 20244,419
September 202419,450
August 202418,165
July 202421,331
June 202421,730
May 202423,805
April 202421,729
March 20244,665
February 2024246
January 2024234

Source: EIA Form EIA-923, through August 2026.

How much of Colorado's electricity comes from the Flatiron plant?

Flatiron made 0.4% of the 55,830,894 MWh reported by Colorado plants in 2025, from 0.4% of the state's 22,712 MW of capacity. By capacity it is the 64th largest of 321 plants in Colorado, the 2,808th largest of 14,327 in the U.S. and the 182nd largest of 1,393 hydro plants on its hydro units alone. By 2025 generation it is the 49th largest of 292 generating plants in the state.

Flatiron within Colorado, 2025
MeasureThis plantColoradoShare
Capacity (MW)9522,7120.4%
Generation (MWh)214,84555,830,8940.4%
Hydro capacity (MW)8667912.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Flatiron plant, and when do they retire?

3 operable generators total 94.5 MW, with an average age of 71 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1950s395100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric431954n/a
2OperatingConventional Hydroelectric431954n/a
3OperatingHydroelectric Pumped Storage91954n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Flatiron plant?

EIA lists no joint owners for Flatiron. U S Bureau of Reclamation operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What fuels does the Flatiron plant use?

Flatiron has capacity on 2 fuels: 91% hydro and 9% battery and pumped storage. In 2025, hydro made 121% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Hydro8691.0%259,076
Battery and pumped storage99.0%-44,231

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Flatiron plant?

Flatiron is in Loveland, Larimer County, Colorado, at 40.3650° N, 105.2360° W. It sits in the Western Area Power Administration - Rocky Mountain Region balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Colorado are similar in size?

Colorado has 47 operable hydro plants with 679 MW of capacity, and Flatiron's 86 MW is 13% of that.

Hydro plants in Colorado around this size
PlantCountyMW2025 MWh
Blue MesaGunnison86198,014
FlatironLarimer86259,076
EstesLarimer45123,394

Source: EIA Forms EIA-860 and EIA-923, 2025.