Solar power plant, Texas
Fort Bend Solar LLC power plant, Texas
Fort Bend Solar LLC is a 240 MW solar power plant in Fort Bend County, Texas, operated by Acciona Energy USA Global, LLC, and it generated 527,197 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 65th percentile of U.S. solar plants. By 2025 generation it ranks 1,286th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Fort Bend Solar LLC plant run compared with other solar plants?
The Fort Bend Solar LLC plant had a capacity factor of 25% in 2025 on 240 MW of net summer capacity, the 65th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 92 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Fort Bend Solar LLC | 25% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Fort Bend Solar LLC plant generating more or less than last year?
Generation at Fort Bend Solar LLC rose 22.6% from 2024 to 2025, from 430,043 MWh to 527,197 MWh. Through August 2026 it is running 6.4% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 430,043 |
| 2025 | 527,197 |
| 2026 through August | 384,450 |
| 2025, same months | 361,243 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 61,410 |
| July 2026 | 59,119 |
| June 2026 | 52,021 |
| May 2026 | 52,676 |
| April 2026 | 33,682 |
| March 2026 | 51,939 |
| February 2026 | 40,701 |
| January 2026 | 32,902 |
| December 2025 | 26,865 |
| November 2025 | 37,568 |
| October 2025 | 46,778 |
| September 2025 | 54,743 |
| August 2025 | 53,407 |
| July 2025 | 54,357 |
| June 2025 | 54,936 |
| May 2025 | 55,718 |
| April 2025 | 48,553 |
| March 2025 | 48,031 |
| February 2025 | 24,984 |
| January 2025 | 21,257 |
| December 2024 | 16,807 |
| November 2024 | 21,487 |
| October 2024 | 43,196 |
| September 2024 | 42,724 |
| August 2024 | 48,411 |
| July 2024 | 43,398 |
| June 2024 | 54,716 |
| May 2024 | 40,093 |
| April 2024 | 44,215 |
| March 2024 | 31,542 |
| February 2024 | 20,616 |
| January 2024 | 22,838 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Fort Bend Solar LLC plant, and when do they retire?
1 operable generator totals 240 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 240 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| FBS | Operating | Solar Photovoltaic | 240 | 2023 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Fort Bend Solar LLC plant?
EIA lists no joint owners for Fort Bend Solar LLC. Acciona Energy USA Global, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Fort Bend Solar LLC plant?
Fort Bend Solar LLC is in East Bernard, Fort Bend County, Texas, at 29.5603° N, 95.9804° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Texas are similar in size?
Texas has 225 operable solar plants with 30,739 MW of capacity, and Fort Bend Solar LLC's 240 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Roaring Springs, LLC | Motley | 250 | 91,658 |
| Porter Solar, LLC (TX) | Denton | 245 | 556,333 |
| Misae Solar | Childress | 240 | 408,882 |
| Fort Bend Solar LLC | Fort Bend | 240 | 527,197 |
| 7V Solar Ranch | Fayette | 240 | 501,270 |
| Eiffel Solar Project | Lamar | 240 | 573,603 |
| True North Solar, LLC | Falls | 239 | 556,356 |
Source: EIA Forms EIA-860 and EIA-923, 2025.