Skip to main content
RateWatt

Natural gas power plant, Iowa

Gas Turbine natural gas power plant, Iowa

Gas Turbine (IA) is a 43.4 MW natural gas power plant in Black Hawk County, Iowa, operated by Cedar Falls Utilities, and it generated 1,056 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 3rd percentile of U.S. natural gas plants. By 2025 generation it ranks 11,820th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

43.4 MWNameplate capacity
under 1%Capacity factor, 2025, 3rd percentile, on 40.3 MW net summer
11,820thU.S. rank by generation, 2025
39 yearsAverage generator age, by MW

How hard does the Gas Turbine (IA) plant run compared with other natural gas plants?

The Gas Turbine (IA) plant had a capacity factor of under 1% in 2025 on 40.3 MW of net summer capacity, the 3rd percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. It ran for only a few hours of the year at full output.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Gas Turbine (IA)under 1%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Gas Turbine (IA) plant generating more or less than last year?

Generation at Gas Turbine (IA) rose 53.0% from 2024 to 2025, from 690 MWh to 1,056 MWh.

Net generation by period
PeriodMWh
2024690
20251,056
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202579
November 202564
October 202564
September 2025132
August 2025145
July 2025129
June 2025102
May 202585
April 202554
March 202557
February 202569
January 202577
December 202456
November 202443
October 202437
September 202466
August 202494
July 202493
June 202466
May 202465
April 202422
March 202434
February 202455
January 202460

Source: EIA Form EIA-923, through August 2026.

How much of Iowa's electricity comes from the Gas Turbine (IA) plant?

Gas Turbine (IA) made 0.0% of the 74,502,373 MWh reported by Iowa plants in 2025, from 0.2% of the state's 24,817 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 109th largest of 306 plants in Iowa, the 4,012th largest of 14,327 in the U.S. and the 1,140th largest of 1,962 natural gas plants. By 2025 generation it is the 197th largest of 283 generating plants in the state.

Gas Turbine (IA) within Iowa, 2025
MeasureThis plantIowaShare
Capacity (MW)4324,8170.2%
Generation (MWh)1,05674,502,3730.0%
Natural gas capacity (MW)434,2811.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Gas Turbine (IA) plant, and when do they retire?

2 operable generators total 43.4 MW, with an average age of 39 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1960s12045%none reported
2000s12455%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingNatural Gas Fired Combustion Turbine201968n/a
2OperatingNatural Gas Fired Combustion Turbine242000n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Gas Turbine (IA) plant?

EIA lists no joint owners for Gas Turbine (IA). Cedar Falls Utilities operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Cedar Falls Utilities charge homes?

Cedar Falls Utilities, the operator of Gas Turbine (IA), had an average residential price of 11.56¢ per kWh and an average bill of $97 a month in 2025, 15% below the Iowa average of 13.62¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Iowa
Cedar Falls Utilities11.56¢$9715% lower
Iowa average13.62¢$117
U.S. average17.23¢$15126% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Gas Turbine (IA) plant?

Gas Turbine (IA) is in Cedar Falls, Black Hawk County, Iowa, at 42.5120° N, 92.4760° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Iowa are similar in size?

Iowa has 38 operable natural gas plants with 4,281 MW of capacity, and Gas Turbine (IA)'s 43.4 MW is 1% of that.

Natural gas plants in Iowa around this size
PlantCountyMW2025 MWh
Coralville GTJohnson722,498
Streeter StationBlack Hawk5213,415
Roquette AmericaLee50207,375
Gas Turbine (IA)Black Hawk431,056
Cargill Corn Milling DivisionMonroe40112,073
Iowa State UniversityStory4080,930
University of Iowa Main Power PlantJohnson390

Source: EIA Forms EIA-860 and EIA-923, 2025.