Skip to main content
RateWatt

Natural gas power plant, Florida

Greenland Energy Center, Florida

Greenland Energy Center is a 381 MW natural gas power plant in Duval County, Florida, operated by Jea, and it generated 658,098 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Florida, and its capacity factor sits at the 49th percentile of U.S. natural gas plants. By 2025 generation it ranks 1,043rd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

381 MWNameplate capacity
21%Capacity factor, 2025, 49th percentile, on 357 MW net summer
0.2%Of FL generation, 2025
14 yearsAverage generator age, by MW

How hard does the Greenland Energy Center plant run compared with other natural gas plants?

The Greenland Energy Center plant had a capacity factor of 21% in 2025 on 357 MW of net summer capacity, the 49th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 76 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Greenland Energy Center21%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Greenland Energy Center plant generating more or less than last year?

Generation at Greenland Energy Center fell 14.6% from 2024 to 2025, from 770,877 MWh to 658,098 MWh.

Net generation by period
PeriodMWh
2024770,877
2025658,098
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20257,967
November 202525,020
October 202521,054
September 202571,067
August 202573,439
July 202593,639
June 202544,139
May 202564,461
April 202589,133
March 202567,315
February 202555,420
January 202545,445
December 202449,811
November 202468,722
October 202423,849
September 202472,709
August 202489,181
July 2024108,034
June 202485,969
May 202465,511
April 2024138,718
March 202422,013
February 202426,160
January 202420,200

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Greenland Energy Center plant?

Greenland Energy Center made 0.2% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.5% of the state's 79,936 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 44th largest of 331 plants in Florida, the 878th largest of 14,327 in the U.S. and the 529th largest of 1,962 natural gas plants. By 2025 generation it is the 38th largest of 313 generating plants in the state.

Greenland Energy Center within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)38179,9360.5%
Generation (MWh)658,098267,867,7350.2%
Natural gas capacity (MW)38152,8940.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Greenland Energy Center plant, and when do they retire?

2 operable generators total 381 MW, with an average age of 14 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s2381100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingNatural Gas Fired Combustion Turbine1902011n/a
2OperatingNatural Gas Fired Combustion Turbine1902011n/a
3CancelledNatural Gas Fired Combined Cycle230n/an/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Greenland Energy Center plant?

EIA lists no joint owners for Greenland Energy Center. Jea operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does JEA charge homes?

JEA, the operator of Greenland Energy Center, had an average residential price of 13.84¢ per kWh and an average bill of $146 a month in 2025, 9% below the Florida average of 15.21¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Florida
JEA13.84¢$1469% lower
Florida average15.21¢$168
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Greenland Energy Center plant?

Greenland Energy Center is in Jacksonville, Duval County, Florida, at 30.1591° N, 81.5184° W. It sits in the JEA balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Florida are similar in size?

Florida has 68 operable natural gas plants with 52,894 MW of capacity, and Greenland Energy Center's 381 MW is 1% of that.

Natural gas plants in Florida around this size
PlantCountyMW2025 MWh
Deerhaven Generating StationAlachua471617,957
Hardee Power StationHardee470792,540
Treasure Coast Energy CenterSt Lucie4111,747,433
Greenland Energy CenterDuval381654,854
J D KennedyDuval370308,298
Indian River PlantBrevard3434,349
Tiger BayPolk278761,923

Source: EIA Forms EIA-860 and EIA-923, 2025.