Harrison County Power Project, Texas

Harrison County Power Project is a 570 MW natural gas power plant in Harrison County, Texas, operated by Northeast Texas Elec Coop, Inc, and it generated 2,565,558 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Texas, and its capacity factor sits at the 76th percentile of U.S. natural gas plants. By 2025 generation it ranks 435th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

570 MWNameplate capacity
57%Capacity factor, 2025, 76th percentile, on 514 MW net summer
0.4%Of TX generation, 2025
22 yearsAverage generator age, by MW

How hard does the Harrison County Power Project plant run compared with other natural gas plants?

The Harrison County Power Project plant had a capacity factor of 57% in 2025 on 514 MW of net summer capacity, the 76th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 208 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Harrison County Power Project57%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Harrison County Power Project plant generating more or less than last year?

Harrison County Power Project generated 2,565,558 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 26.1% ahead of the same months of 2025. 2024 has output for only 11 months, so the two years are not compared.

Net generation by period
PeriodMWh
20243,247,919
20252,565,558
2026 through August2,091,284
2025, same months1,658,133
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026352,536
July 2026343,416
June 2026299,342
May 2026204,992
April 2026301,311
March 2026125,527
February 2026209,911
January 2026254,249
December 2025212,497
November 2025110,268
October 2025314,195
September 2025270,465
August 2025340,744
July 2025332,385
June 2025326,163
May 202535,844
April 20250
March 202593,466
February 2025173,568
January 2025355,963
December 2024333,416
November 2024161,630
October 2024292,728
September 2024316,421
August 2024353,046
July 2024356,942
June 2024306,698
May 202497,683
April 20240
March 2024338,853
February 2024323,492
January 2024367,010

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Harrison County Power Project plant?

Harrison County Power Project made 0.4% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.3% of the state's 195,966 MW of capacity. Its share of output is 1.5 times its share of capacity. By capacity it is the 80th largest of 1,023 plants in Texas, the 650th largest of 14,327 in the U.S. and the 405th largest of 1,962 natural gas plants. By 2025 generation it is the 56th largest of 816 generating plants in the state.

Harrison County Power Project within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)570195,9660.3%
Generation (MWh)2,565,558592,896,1760.4%
Natural gas capacity (MW)57081,5740.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Harrison County Power Project plant, and when do they retire?

3 operable generators total 570 MW, with an average age of 22 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s3570100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GT-1OperatingNatural Gas Fired Combined Cycle1702003n/a
GT-2OperatingNatural Gas Fired Combined Cycle1702003n/a
ST-1OperatingNatural Gas Fired Combined Cycle2302003n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Harrison County Power Project plant?

2 owners report shares in Harrison County Power Project; Northeast Texas Elec Coop, Inc holds the largest named share, 55.0% or about 314 MW. Northeast Texas Elec Coop, Inc operates the plant.

Reported ownership of operable capacity
OwnerShareMW2025 MWh, by share
Northeast Texas Elec Coop, Inc55.0%3141,411,057
East Texas Electric Coop, Inc45.0%2571,154,501

Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.

Where is the Harrison County Power Project plant?

Harrison County Power Project is in Marshall, Harrison County, Texas, at 32.3958° N, 94.4367° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Texas are similar in size?

Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Harrison County Power Project's 570 MW is 1% of that.

Natural gas plants in Texas around this size
PlantCountyMW2025 MWh
Arthur Von RosenbergBexar5753,613,377
Thomas C FergusonLlano5753,630,050
Sweeny Cogen FacilityBrazoria5722,300,495
Harrison County Power ProjectHarrison5702,565,558
Hidalgo Energy CenterHidalgo5512,721,492
Quail Run Energy CenterEctor5503,081,998
Lewis CreekMontgomery5431,867,914

Source: EIA Forms EIA-860 and EIA-923, 2025.