Petroleum power plant, New York
Hawkeye Energy Greenport LLC petroleum power plant, New York
Hawkeye Energy Greenport LLC is a 54 MW petroleum power plant in SUFFOLK County, New York, operated by Hawkeye Energy Greenport LLC, and it generated 24,868 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 85th percentile of U.S. petroleum plants. By 2025 generation it ranks 4,965th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Hawkeye Energy Greenport LLC plant run compared with other petroleum plants?
The Hawkeye Energy Greenport LLC plant had a capacity factor of 5% in 2025 on 54.5 MW of net summer capacity, the 85th percentile of the 143 U.S. petroleum plants with at least 20 MW. The typical petroleum plant reached 1%. That equals about 19 days at full output out of 365.
0%Shaded: the middle half of petroleum plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Hawkeye Energy Greenport LLC | 5% |
| Petroleum plants, 75th percentile | 1% |
| Petroleum plants, median | 1% |
| Petroleum plants, 25th percentile | 0% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Hawkeye Energy Greenport LLC plant generating more or less than last year?
Hawkeye Energy Greenport LLC generated 24,868 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 24,819 |
| 2025 | 24,868 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,120 |
| November 2025 | 0 |
| October 2025 | 0 |
| September 2025 | 517 |
| August 2025 | 3,818 |
| July 2025 | 9,640 |
| June 2025 | 2,542 |
| May 2025 | 625 |
| April 2025 | 113 |
| March 2025 | 14 |
| February 2025 | 2,821 |
| January 2025 | 3,658 |
| December 2024 | 1,686 |
| November 2024 | 296 |
| October 2024 | 0 |
| September 2024 | 150 |
| August 2024 | 6,354 |
| July 2024 | 10,008 |
| June 2024 | 3,410 |
| May 2024 | 562 |
| April 2024 | 508 |
| March 2024 | 227 |
| February 2024 | 1,137 |
| January 2024 | 481 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Hawkeye Energy Greenport LLC plant, and when do they retire?
1 operable generator totals 54 MW, with an average age of 22 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 54 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| U-01 | Operating | Petroleum Liquids | 54 | 2003 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Hawkeye Energy Greenport LLC plant?
EIA lists no joint owners for Hawkeye Energy Greenport LLC. Hawkeye Energy Greenport LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Hawkeye Energy Greenport LLC plant?
Hawkeye Energy Greenport LLC is in Greenport, SUFFOLK County, New York, at 41.1060° N, 72.3762° W. It sits in the New York Independent System Operator balancing area (NERC region NPCC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which petroleum plants in New York are similar in size?
New York has 70 operable petroleum plants with 3,462 MW of capacity, and Hawkeye Energy Greenport LLC's 54 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Shoreham Energy LLC | Suffolk | 100 | 4,248 |
| Shoreham | Suffolk | 72 | 1,003 |
| Jamaica Bay Peaking | Queens | 61 | 23,009 |
| Hawkeye Energy Greenport LLC | SUFFOLK | 54 | 24,868 |
| West Babylon | Suffolk | 52 | n/a |
| 74th Street | New York | 37 | 54 |
| Regeneron Pharmaceuticals Inc. | Westchester | 30 | 217 |
Source: EIA Forms EIA-860 and EIA-923, 2025.