Petroleum power plant, New York
Shoreham Energy LLC petroleum power plant, New York
Shoreham Energy LLC is a 100 MW petroleum power plant in Suffolk County, New York, operated by MPH Cross Island Power, and it generated 4,248 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 52nd percentile of U.S. petroleum plants. By 2025 generation it ranks 8,498th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Shoreham Energy LLC plant run compared with other petroleum plants?
The Shoreham Energy LLC plant had a capacity factor of under 1% in 2025 on 85 MW of net summer capacity, the 52nd percentile of the 143 U.S. petroleum plants with at least 20 MW. The typical petroleum plant reached 1%. It ran for only a few hours of the year at full output.
0%Shaded: the middle half of petroleum plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Shoreham Energy LLC | under 1% |
| Petroleum plants, 75th percentile | 1% |
| Petroleum plants, median | 1% |
| Petroleum plants, 25th percentile | 0% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Shoreham Energy LLC plant generating more or less than last year?
Shoreham Energy LLC generated 4,248 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 1,463 |
| 2025 | 4,248 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 266 |
| November 2025 | 95 |
| October 2025 | 188 |
| September 2025 | 2 |
| August 2025 | 824 |
| July 2025 | 745 |
| June 2025 | 457 |
| May 2025 | 0 |
| April 2025 | 6 |
| March 2025 | 277 |
| February 2025 | 154 |
| January 2025 | 1,235 |
| December 2024 | 53 |
| November 2024 | 28 |
| October 2024 | 63 |
| September 2024 | 345 |
| August 2024 | 142 |
| July 2024 | 316 |
| June 2024 | 309 |
| May 2024 | 67 |
| April 2024 | 133 |
| March 2024 | 2 |
| February 2024 | 0 |
| January 2024 | 5 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Shoreham Energy LLC plant, and when do they retire?
2 operable generators total 100 MW, with an average age of 23 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 2 | 100 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CT01 | Operating | Petroleum Liquids | 50 | 2002 | n/a |
| CT02 | Operating | Petroleum Liquids | 50 | 2002 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Shoreham Energy LLC plant?
EIA lists no joint owners for Shoreham Energy LLC. MPH Cross Island Power operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Shoreham Energy LLC plant?
Shoreham Energy LLC is in Shoreham, Suffolk County, New York, at 40.9571° N, 72.8659° W. It sits in the New York Independent System Operator balancing area (NERC region NPCC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which petroleum plants in New York are similar in size?
New York has 70 operable petroleum plants with 3,462 MW of capacity, and Shoreham Energy LLC's 100 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Glenwood | Nassau | 110 | 4,559 |
| Shoreham Energy LLC | Suffolk | 100 | 4,248 |
| Shoreham | Suffolk | 72 | 1,003 |
| Jamaica Bay Peaking | Queens | 61 | 23,009 |
| Hawkeye Energy Greenport LLC | SUFFOLK | 54 | 24,868 |
Source: EIA Forms EIA-860 and EIA-923, 2025.