Solar power plant, Georgia
Hazlehurst II solar power plant, Georgia
Hazlehurst II is a 52.5 MW solar power plant in Jeff Davis County, Georgia, operated by SR South Loving, LLC, and it generated 62,114 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 10th percentile of U.S. solar plants. By 2025 generation it ranks 3,846th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Hazlehurst II plant run compared with other solar plants?
The Hazlehurst II plant had a capacity factor of 14% in 2025 on 52.5 MW of net summer capacity, the 10th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 49 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Hazlehurst II | 14% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Hazlehurst II plant generating more or less than last year?
Generation at Hazlehurst II fell 27.7% from 2024 to 2025, from 85,866 MWh to 62,114 MWh. Through August 2026 it is running 3.9% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 85,866 |
| 2025 | 62,114 |
| 2026 through August | 46,441 |
| 2025, same months | 48,314 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 10,394 |
| July 2026 | 11,375 |
| June 2026 | 10,686 |
| May 2026 | 3,024 |
| April 2026 | 3,390 |
| March 2026 | 3,252 |
| February 2026 | 2,164 |
| January 2026 | 2,156 |
| December 2025 | 1,672 |
| November 2025 | 2,121 |
| October 2025 | 7,317 |
| September 2025 | 2,690 |
| August 2025 | 2,251 |
| July 2025 | 2,252 |
| June 2025 | 9,071 |
| May 2025 | 8,506 |
| April 2025 | 8,768 |
| March 2025 | 7,334 |
| February 2025 | 5,164 |
| January 2025 | 4,968 |
| December 2024 | 4,268 |
| November 2024 | 4,050 |
| October 2024 | 4,771 |
| September 2024 | 5,281 |
| August 2024 | 8,545 |
| July 2024 | 8,552 |
| June 2024 | 10,735 |
| May 2024 | 9,479 |
| April 2024 | 10,158 |
| March 2024 | 8,394 |
| February 2024 | 6,360 |
| January 2024 | 5,273 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Hazlehurst II plant, and when do they retire?
1 operable generator totals 52.5 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 53 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| STHLV | Operating | Solar Photovoltaic | 53 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Hazlehurst II plant?
EIA lists no joint owners for Hazlehurst II. SR South Loving, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Hazlehurst II plant?
Hazlehurst II is in Hazlehurst, Jeff Davis County, Georgia, at 31.8194° N, 82.6022° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Georgia are similar in size?
Georgia has 152 operable solar plants with 5,414 MW of capacity, and Hazlehurst II's 52.5 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| SR DeSoto II | Lee | 65 | 153,120 |
| SR DeSoto III | Lee | 60 | 135,019 |
| OE_GA3 | Mitchell | 58 | 123,829 |
| Hazlehurst II | Jeff Davis | 53 | 62,114 |
| Live Oak Solar, LLC | Candler | 51 | 84,464 |
| Moody Air Force Base Solar | Lowndes | 50 | 84,201 |
| Hazlehurst III | Jeff Davis | 40 | 73,196 |
Source: EIA Forms EIA-860 and EIA-923, 2025.