Natural gas power plant, Pennsylvania
Hill Top Energy Center, LLC natural gas power plant, Pennsylvania
Hill Top Energy Center, LLC is a 665 MW natural gas power plant in Greene County, Pennsylvania, operated by Hill Top Energy Center, LLC, and it generated 4,258,836 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.7% of the generation reported in Pennsylvania, and its capacity factor sits at the 91st percentile of U.S. natural gas plants. By 2025 generation it ranks 268th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Hill Top Energy Center, LLC plant run compared with other natural gas plants?
The Hill Top Energy Center, LLC plant had a capacity factor of 78% in 2025 on 624 MW of net summer capacity, the 91st percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 285 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Hill Top Energy Center, LLC | 78% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Hill Top Energy Center, LLC plant generating more or less than last year?
Generation at Hill Top Energy Center, LLC fell 16.4% from 2024 to 2025, from 5,091,305 MWh to 4,258,836 MWh. Through August 2026 it is running 3.4% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 5,091,305 |
| 2025 | 4,258,836 |
| 2026 through August | 3,187,699 |
| 2025, same months | 3,300,160 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 451,595 |
| July 2026 | 441,390 |
| June 2026 | 404,185 |
| May 2026 | 418,782 |
| April 2026 | 263,632 |
| March 2026 | 439,045 |
| February 2026 | 385,799 |
| January 2026 | 383,271 |
| December 2025 | 411,983 |
| November 2025 | 98,256 |
| October 2025 | 6,344 |
| September 2025 | 442,093 |
| August 2025 | 451,193 |
| July 2025 | 451,716 |
| June 2025 | 428,584 |
| May 2025 | 445,385 |
| April 2025 | 348,994 |
| March 2025 | 450,325 |
| February 2025 | 298,562 |
| January 2025 | 425,401 |
| December 2024 | 432,800 |
| November 2024 | 440,939 |
| October 2024 | 315,606 |
| September 2024 | 439,776 |
| August 2024 | 451,988 |
| July 2024 | 456,947 |
| June 2024 | 432,067 |
| May 2024 | 458,842 |
| April 2024 | 327,735 |
| March 2024 | 455,929 |
| February 2024 | 430,919 |
| January 2024 | 447,757 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Hill Top Energy Center, LLC plant, and when do they retire?
1 operable generator totals 665 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 665 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Natural Gas Fired Combined Cycle | 665 | 2021 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Hill Top Energy Center, LLC plant?
EIA lists no joint owners for Hill Top Energy Center, LLC. Hill Top Energy Center, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Hill Top Energy Center, LLC plant?
Hill Top Energy Center, LLC is in Carmichaels, Greene County, Pennsylvania, at 39.8942° N, 79.9382° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Pennsylvania are similar in size?
Pennsylvania has 70 operable natural gas plants with 29,880 MW of capacity, and Hill Top Energy Center, LLC's 665 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Ontelaunee Energy Center | Berks | 728 | 4,114,446 |
| Fayette Energy Facility | Fayette | 715 | 4,586,211 |
| Armstrong | Armstrong | 688 | 1,275,382 |
| Hill Top Energy Center, LLC | Greene | 665 | 4,258,836 |
| Lower Mount Bethel Energy | Northampton | 652 | 4,484,858 |
| Shawville | Clearfield | 626 | 1,054,049 |
| Liberty Electric Power Plant | Delaware | 614 | 3,931,943 |
Source: EIA Forms EIA-860 and EIA-923, 2025.