Hydro power plant, Nevada
Hoover Dam, Nevada
Hoover Dam (NV) is a 1,039 MW hydro power plant in Clark County, Nevada, operated by U S Bureau of Reclamation, and it generated 1,807,912 MWh in 2025 (Forms EIA-860 and EIA-923). That is 4.0% of the generation reported in Nevada, and its capacity factor sits at the 20th percentile of U.S. hydro plants. By 2025 generation it ranks 539th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Hoover Dam (NV) plant run compared with other hydro plants?
The Hoover Dam (NV) plant had a capacity factor of 20% in 2025 on 1,039 MW of net summer capacity, the 20th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 72 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Hoover Dam (NV) | 20% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Hoover Dam (NV) plant generating more or less than last year?
Generation at Hoover Dam (NV) rose 18.0% from 2024 to 2025, from 1,531,949 MWh to 1,807,912 MWh. Through August 2026 it is running 35.1% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 1,531,949 |
| 2025 | 1,807,912 |
| 2026 through August | 975,180 |
| 2025, same months | 1,502,836 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 126,813 |
| July 2026 | 151,462 |
| June 2026 | 195,695 |
| May 2026 | 207,292 |
| April 2026 | 134,974 |
| March 2026 | 86,537 |
| February 2026 | 42,471 |
| January 2026 | 29,936 |
| December 2025 | 35,476 |
| November 2025 | 60,430 |
| October 2025 | 108,041 |
| September 2025 | 101,129 |
| August 2025 | 152,270 |
| July 2025 | 170,947 |
| June 2025 | 179,380 |
| May 2025 | 255,396 |
| April 2025 | 258,334 |
| March 2025 | 214,546 |
| February 2025 | 145,011 |
| January 2025 | 126,952 |
| December 2024 | 126,767 |
| November 2024 | 137,691 |
| October 2024 | 140,513 |
| September 2024 | 84,254 |
| August 2024 | 104,007 |
| July 2024 | 130,387 |
| June 2024 | 180,030 |
| May 2024 | 203,942 |
| April 2024 | 184,175 |
| March 2024 | 142,446 |
| February 2024 | 47,077 |
| January 2024 | 50,660 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Hoover Dam (NV) plant, and when do they retire?
9 operable generators total 1,039 MW, with an average age of 84 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1930s | 7 | 782 | 75% | none reported |
| 1940s | 1 | 127 | 12% | none reported |
| 1960s | 1 | 130 | 13% | none reported |
Every generator, 9 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| N0 | Operating | Conventional Hydroelectric | 2 | 1936 | n/a |
| N1 | Operating | Conventional Hydroelectric | 130 | 1936 | n/a |
| N2 | Operating | Conventional Hydroelectric | 130 | 1936 | n/a |
| N4 | Operating | Conventional Hydroelectric | 130 | 1936 | n/a |
| N3 | Operating | Conventional Hydroelectric | 130 | 1937 | n/a |
| N5 | Operating | Conventional Hydroelectric | 130 | 1938 | n/a |
| N6 | Operating | Conventional Hydroelectric | 130 | 1938 | n/a |
| N7 | Operating | Conventional Hydroelectric | 127 | 1944 | n/a |
| N8 | Operating | Conventional Hydroelectric | 130 | 1961 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Hoover Dam (NV) plant?
EIA lists no joint owners for Hoover Dam (NV). U S Bureau of Reclamation operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Hoover Dam (NV) plant?
Hoover Dam (NV) is in Boulder City, Clark County, Nevada, at 36.0155° N, 114.7380° W. It sits in the Western Area Power Administration - Desert Southwest Region balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.