Hydro power plant, Iowa
Keokuk hydroelectric power plant, Iowa
Keokuk is a 125 MW hydro power plant in Lee County, Iowa, operated by Union Electric Co-(MO), and it generated 961,805 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.3% of the generation reported in Iowa, and its capacity factor sits at the 98th percentile of U.S. hydro plants. By 2025 generation it ranks 756th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Keokuk plant run compared with other hydro plants?
The Keokuk plant had a capacity factor of 73% in 2025 on 150 MW of net summer capacity, the 98th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 267 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Keokuk | 73% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Keokuk plant generating more or less than last year?
Generation at Keokuk rose 8.3% from 2024 to 2025, from 888,279 MWh to 961,805 MWh.
| Period | MWh |
|---|---|
| 2024 | 888,279 |
| 2025 | 961,805 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 57,876 |
| November 2025 | 57,346 |
| October 2025 | 66,869 |
| September 2025 | 91,934 |
| August 2025 | 92,555 |
| July 2025 | 88,352 |
| June 2025 | 97,211 |
| May 2025 | 100,699 |
| April 2025 | 96,404 |
| March 2025 | 101,405 |
| February 2025 | 51,500 |
| January 2025 | 59,654 |
| December 2024 | 65,867 |
| November 2024 | 73,913 |
| October 2024 | 48,883 |
| September 2024 | 66,143 |
| August 2024 | 98,945 |
| July 2024 | 54,036 |
| June 2024 | 74,579 |
| May 2024 | 83,746 |
| April 2024 | 94,630 |
| March 2024 | 73,457 |
| February 2024 | 82,912 |
| January 2024 | 71,168 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Keokuk plant, and when do they retire?
15 operable generators total 125 MW, with an average age of 112 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1910s | 15 | 125 | 100% | none reported |
Every generator, 15 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 8 | 1913 | n/a |
| 2 | Operating | Conventional Hydroelectric | 8 | 1913 | n/a |
| 3 | Operating | Conventional Hydroelectric | 8 | 1913 | n/a |
| 4 | Operating | Conventional Hydroelectric | 8 | 1913 | n/a |
| 5 | Operating | Conventional Hydroelectric | 8 | 1913 | n/a |
| 6 | Operating | Conventional Hydroelectric | 8 | 1913 | n/a |
| 7 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 8 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 9 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 10 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 11 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 12 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 13 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 14 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
| 15 | Operating | Conventional Hydroelectric | 9 | 1913 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Keokuk plant?
EIA lists no joint owners for Keokuk. Union Electric Co-(MO) operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Union Electric Co charge homes?
Union Electric Co, the operator of Keokuk, had an average residential price of 13.27¢ per kWh and an average bill of $137 a month in 2025 in Missouri.
| Measure | Price | Monthly bill | Against Iowa |
|---|---|---|---|
| Union Electric Co | 13.27¢ | $137 | other state |
| Iowa average | 13.62¢ | $117 | |
| U.S. average | 17.23¢ | $151 | 26% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Keokuk plant?
Keokuk is in Keokuk, Lee County, Iowa, at 40.3965° N, 91.3719° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.