Coal power plant, Tennessee

Kingston coal power plant, Tennessee

Kingston is a 1,700 MW coal power plant in Roane County, Tennessee, operated by Tennessee Valley Authority, and it generated 3,382,008 MWh in 2025 (Forms EIA-860 and EIA-923). That is 4.5% of the generation reported in Tennessee, and its capacity factor sits at the 21st percentile of U.S. coal plants. By 2025 generation it ranks 349th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

1,700 MWNameplate capacity
34%Capacity factor, 2025, 21st percentile, on 1,147 MW net summer
4.5%Of TN generation, 2025
70 yearsAverage generator age, by MW

How hard does the Kingston plant run compared with other coal plants?

The Kingston plant had a capacity factor of 34% in 2025 on 1,147 MW of net summer capacity, the 21st percentile of the 181 U.S. coal plants with at least 20 MW. The typical coal plant reached 49%. That equals about 123 days at full output out of 365.

0%Shaded: the middle half of coal plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Kingston34%
Coal plants, 75th percentile63%
Coal plants, median49%
Coal plants, 25th percentile37%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Kingston plant generating more or less than last year?

Generation at Kingston fell 2.3% from 2024 to 2025, from 3,460,569 MWh to 3,382,008 MWh. Through August 2026 it is running 5.2% behind the same months of 2025.

Net generation by period
PeriodMWh
20243,460,569
20253,382,008
2026 through August2,327,629
2025, same months2,454,910
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026416,564
July 2026383,298
June 2026268,748
May 2026234,699
April 2026242,240
March 2026166,516
February 2026281,259
January 2026334,305
December 2025229,929
November 2025237,217
October 2025185,358
September 2025274,594
August 2025412,437
July 2025503,989
June 2025334,860
May 2025210,545
April 2025132,361
March 2025269,817
January 2025590,901
December 2024302,617
November 2024204,347
October 2024211,215
September 2024361,177
August 2024430,331
July 2024385,363
June 2024324,175
May 2024260,681
April 2024152,807
March 2024223,442
February 2024232,356
January 2024372,058

Source: EIA Form EIA-923, through August 2026.

How much of Tennessee's electricity comes from the Kingston plant?

Kingston made 4.5% of the 74,359,316 MWh reported by Tennessee plants in 2025, from 7.3% of the state's 23,342 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 6th largest of 99 plants in Tennessee, the 116th largest of 14,327 in the U.S. and the 31st largest of 195 coal plants. By 2025 generation it is the 8th largest of 95 generating plants in the state.

Kingston within Tennessee, 2025
MeasureThis plantTennesseeShare
Capacity (MW)1,70023,3427.3%
Generation (MWh)3,382,00874,359,3164.5%
Coal capacity (MW)1,7005,66630.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Kingston plant, and when do they retire?

9 operable generators total 1,700 MW, with an average age of 70 years weighted by capacity at the end of 2025. 1,700 MW, 100% of operable capacity, has a planned retirement, the first in 2027. 18 more are proposed, totalling 1,831 MW.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1950s91,700100%2027, 2034
Capacity retiring by year
YearUnitsMW retiringShare of plant
202761,10065%
2034360035%
Every generator, 27 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Steam Coal17519542027
2OperatingConventional Steam Coal17519542027
3OperatingConventional Steam Coal17519542027
4OperatingConventional Steam Coal17519542027
5OperatingConventional Steam Coal20019552027
6OperatingConventional Steam Coal20019552027
7OperatingConventional Steam Coal20019552034
8OperatingConventional Steam Coal20019552034
9OperatingConventional Steam Coal20019552034
CTG1Planned, not yet approvedNatural Gas Fired Combined Cycle4552027n/a
G1Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G2Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G3Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G4Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G5Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G6Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G7Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G8Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G9Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G10Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G11Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G12Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G13Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G14Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G15Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
G16Planned, not yet approvedNatural Gas Fired Combustion Turbine662027n/a
STG1Planned, not yet approvedNatural Gas Fired Combined Cycle3232027n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Kingston plant?

EIA lists no joint owners for Kingston. Tennessee Valley Authority operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Kingston plant?

Kingston is in Kingston, Roane County, Tennessee, at 35.8992° N, 84.5194° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which coal plants in Tennessee are similar in size?

Tennessee has 4 operable coal plants with 5,666 MW of capacity, and Kingston's 1,700 MW is 30% of that.

Coal plants in Tennessee around this size
PlantCountyMW2025 MWh
Cumberland (TN)Stewart2,6008,998,397
KingstonRoane1,7003,372,500
Gallatin (TN)Sumner1,2554,196,526

Source: EIA Forms EIA-860 and EIA-923, 2025.