Solar power plant, Florida
Lake Hancock Solar power plant, Florida
Lake Hancock Solar is a 49.5 MW solar power plant in Polk County, Florida, operated by Tampa Electric Co, and it generated 93,030 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 37th percentile of U.S. solar plants. By 2025 generation it ranks 3,475th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Lake Hancock Solar plant run compared with other solar plants?
The Lake Hancock Solar plant had a capacity factor of 21% in 2025 on 49.5 MW of net summer capacity, the 37th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 78 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Lake Hancock Solar | 21% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Lake Hancock Solar plant generating more or less than last year?
Generation at Lake Hancock Solar rose 0.9% from 2024 to 2025, from 92,225 MWh to 93,030 MWh. Through August 2026 it is running 0.4% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 92,225 |
| 2025 | 93,030 |
| 2026 through August | 64,670 |
| 2025, same months | 64,957 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 8,368 |
| July 2026 | 8,639 |
| June 2026 | 9,151 |
| May 2026 | 9,311 |
| April 2026 | 8,560 |
| March 2026 | 8,248 |
| February 2026 | 6,221 |
| January 2026 | 6,172 |
| December 2025 | 5,587 |
| November 2025 | 6,684 |
| October 2025 | 7,962 |
| September 2025 | 7,840 |
| August 2025 | 8,918 |
| July 2025 | 8,495 |
| June 2025 | 8,200 |
| May 2025 | 9,142 |
| April 2025 | 11,030 |
| March 2025 | 8,173 |
| February 2025 | 5,545 |
| January 2025 | 5,454 |
| December 2024 | 5,569 |
| November 2024 | 6,256 |
| October 2024 | 5,602 |
| September 2024 | 7,158 |
| August 2024 | 8,346 |
| July 2024 | 9,461 |
| June 2024 | 9,651 |
| May 2024 | 10,588 |
| April 2024 | 9,993 |
| March 2024 | 7,803 |
| February 2024 | 7,294 |
| January 2024 | 4,504 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Lake Hancock Solar plant, and when do they retire?
1 operable generator totals 49.5 MW, with an average age of 6 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 50 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| PV1 | Operating | Solar Photovoltaic | 50 | 2019 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Lake Hancock Solar plant?
EIA lists no joint owners for Lake Hancock Solar. Tampa Electric Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Tampa Electric Co charge homes?
Tampa Electric Co, the operator of Lake Hancock Solar, had an average residential price of 17.32¢ per kWh and an average bill of $194 a month in 2025, 14% above the Florida average of 15.21¢.
| Measure | Price | Monthly bill | Against Florida |
|---|---|---|---|
| Tampa Electric Co | 17.32¢ | $194 | 14% higher |
| Florida average | 15.21¢ | $168 | |
| U.S. average | 17.23¢ | $151 | 13% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Lake Hancock Solar plant?
Lake Hancock Solar is in Bartow, Polk County, Florida, at 27.7191° N, 82.0339° W. It sits in the Tampa Electric Company balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Florida are similar in size?
Florida has 210 operable solar plants with 12,223 MW of capacity, and Lake Hancock Solar's 49.5 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Mountain View Solar (FL) | Pasco | 55 | 102,520 |
| Citrus Ridge Solar | Orange | 52 | 95,047 |
| Gulf Coast Solar Center III | Escambia | 50 | 93,195 |
| Lake Hancock Solar | Polk | 50 | 93,030 |
| Big Bend II Solar | Hillsborough | 46 | 86,395 |
| Lake Placid Solar Power Plant | Highlands | 45 | 72,837 |
| FL Solar 4, LLC | Leon | 42 | 69,918 |
Source: EIA Forms EIA-860 and EIA-923, 2025.