Lily Solar is a 70 MW solar power plant in Allendale County, South Carolina, operated by X-Elio North America Inc, and it generated 161,974 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in South Carolina, and its capacity factor sits at the 74th percentile of U.S. solar plants. By 2025 generation it ranks 2,793rd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

70 MWNameplate capacity
26%Capacity factor, 2025, 74th percentile, on 70 MW net summer
0.2%Of SC generation, 2025
5 yearsAverage generator age, by MW

How hard does the Lily Solar plant run compared with other solar plants?

The Lily Solar plant had a capacity factor of 26% in 2025 on 70 MW of net summer capacity, the 74th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 96 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Lily Solar26%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Lily Solar plant generating more or less than last year?

Generation at Lily Solar rose 0.8% from 2024 to 2025, from 160,693 MWh to 161,974 MWh. Through August 2026 it is running 3.3% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024160,693
2025161,974
2026 through August119,716
2025, same months115,887
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202617,542
July 202617,541
June 202617,232
May 202615,173
April 202617,078
March 202615,599
February 202610,154
January 20269,397
December 20257,812
November 202511,635
October 202511,706
September 202514,934
August 202512,295
July 202516,774
June 202517,613
May 202515,219
April 202516,883
March 202515,610
February 202510,444
January 202511,049
December 20249,097
November 20249,077
October 202414,232
September 202410,821
August 202415,989
July 202416,317
June 202418,351
May 202416,255
April 202416,800
March 202413,544
February 202410,826
January 20249,384

Source: EIA Form EIA-923, through August 2026.

How much of South Carolina's electricity comes from the Lily Solar plant?

Lily Solar made 0.2% of the 103,930,530 MWh reported by South Carolina plants in 2025, from 0.3% of the state's 27,220 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 52nd largest of 215 plants in South Carolina, the 3,346th largest of 14,327 in the U.S. and the 768th largest of 7,223 solar plants. By 2025 generation it is the 27th largest of 197 generating plants in the state.

Lily Solar within South Carolina, 2025
MeasureThis plantSouth CarolinaShare
Capacity (MW)7027,2200.3%
Generation (MWh)161,974103,930,5300.2%
Solar capacity (MW)701,9563.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Lily Solar plant, and when do they retire?

1 operable generator totals 70 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s170100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingSolar Photovoltaic702020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Lily Solar plant?

EIA lists no joint owners for Lily Solar. X-Elio North America Inc operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Lily Solar plant?

Lily Solar is in Martin, Allendale County, South Carolina, at 33.0949° N, 81.4348° W. It sits in the Dominion Energy South Carolina balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in South Carolina are similar in size?

South Carolina has 126 operable solar plants with 1,956 MW of capacity, and Lily Solar's 70 MW is 4% of that.

Solar plants in South Carolina around this size
PlantCountyMW2025 MWh
Seabrook SolarBeaufort7392,640
MidlandsCalhoun72156,169
Moffett Solar ProjectJasper71138,476
Lily SolarAllendale70161,974
Lone Star SolarCalhoun66165,588
Landrace Holdings, LLCHorry55114,525
Peony SolarOrangeburg3971,391