Solar power plant, Virginia

Maplewood Solar power plant, Virginia

Maplewood Solar is a 120 MW solar power plant in Pittsylvania County, Virginia, operated by Dominion Renewable Energy, and it generated 188,457 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Virginia, and its capacity factor sits at the 16th percentile of U.S. solar plants. By 2025 generation it ranks 2,572nd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

120 MWNameplate capacity
18%Capacity factor, 2025, 16th percentile, on 120 MW net summer
0.2%Of VA generation, 2025
3 yearsAverage generator age, by MW

How hard does the Maplewood Solar plant run compared with other solar plants?

The Maplewood Solar plant had a capacity factor of 18% in 2025 on 120 MW of net summer capacity, the 16th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 65 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Maplewood Solar18%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Maplewood Solar plant generating more or less than last year?

Generation at Maplewood Solar rose 4.1% from 2024 to 2025, from 181,104 MWh to 188,457 MWh. Through August 2026 it is running 10.7% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024181,104
2025188,457
2026 through August150,102
2025, same months135,542
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202618,589
July 202619,269
June 202625,259
May 202624,406
April 202623,667
March 202619,015
February 202610,820
January 20269,077
December 20256,985
November 202511,561
October 202516,504
September 202517,865
August 202517,673
July 202522,218
June 202523,190
May 202514,682
April 202518,698
March 202517,232
February 202511,202
January 202510,647
December 20246,530
November 202410,186
October 202420,330
September 202416,760
August 202424,760
July 202422,305
June 202422,336
May 202419,166
April 202415,091
March 202410,790
February 20248,495
January 20244,355

Source: EIA Form EIA-923, through August 2026.

How much of Virginia's electricity comes from the Maplewood Solar plant?

Maplewood Solar made 0.2% of the 106,220,859 MWh reported by Virginia plants in 2025, from 0.4% of the state's 31,312 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 42nd largest of 259 plants in Virginia, the 2,315th largest of 14,327 in the U.S. and the 380th largest of 7,223 solar plants. By 2025 generation it is the 43rd largest of 241 generating plants in the state.

Maplewood Solar within Virginia, 2025
MeasureThis plantVirginiaShare
Capacity (MW)12031,3120.4%
Generation (MWh)188,457106,220,8590.2%
Solar capacity (MW)1205,1632.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Maplewood Solar plant, and when do they retire?

1 operable generator totals 120 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1120100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
MAPLOperatingSolar Photovoltaic1202022n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Maplewood Solar plant?

EIA lists no joint owners for Maplewood Solar. Dominion Renewable Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Maplewood Solar plant?

Maplewood Solar is in Climax, Pittsylvania County, Virginia, at 36.8900° N, 79.3200° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Virginia are similar in size?

Virginia has 141 operable solar plants with 5,163 MW of capacity, and Maplewood Solar's 120 MW is 2% of that.

Solar plants in Virginia around this size
PlantCountyMW2025 MWh
Chesapeake Solar ProjectChesapeake City132242,848
Bartonsville Energy Facility, LLCFrederick130222,574
Bookers Mill SolarRichmond127170,321
Maplewood SolarPittsylvania120188,457
Waverly Solar, LLCSussex118205,737
Southampton Solar, LLCSouthampton100174,208
Sadler SolarGreensville100183,888

Source: EIA Forms EIA-860 and EIA-923, 2025.