Mesteno is a 202 MW wind power plant in Starr County, Texas, operated by Deriva Energy, and it generated 609,873 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 56th percentile of U.S. wind plants. By 2025 generation it ranks 1,114th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

202 MWNameplate capacity
35%Capacity factor, 2025, 56th percentile, on 200 MW net summer
0.1%Of TX generation, 2025
6 yearsAverage generator age, by MW

How hard does the Mesteno plant run compared with other wind plants?

The Mesteno plant had a capacity factor of 35% in 2025 on 200 MW of net summer capacity, the 56th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 127 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Mesteno35%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Mesteno plant generating more or less than last year?

Generation at Mesteno rose 32.6% from 2024 to 2025, from 460,065 MWh to 609,873 MWh. Through August 2026 it is running 6.8% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024460,065
2025609,873
2026 through August487,932
2025, same months456,784
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202666,905
July 202683,665
June 202665,264
May 202653,007
April 202659,675
March 202677,847
February 202635,545
January 202646,024
December 202535,630
November 202553,195
October 202535,575
September 202528,689
August 202547,620
July 202576,787
June 202560,097
May 202552,869
April 202561,595
March 202564,829
February 202548,645
January 202544,342
December 202443,726
November 202438,969
October 202434,278
September 202430,578
August 202438,906
July 202436,990
June 202440,840
May 202446,450
April 202445,393
March 202441,099
February 202427,271
January 202435,565

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Mesteno plant?

Mesteno made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. By capacity it is the 288th largest of 1,023 plants in Texas, the 1,488th largest of 14,327 in the U.S. and the 244th largest of 1,358 wind plants. By 2025 generation it is the 214th largest of 816 generating plants in the state.

Mesteno within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)202195,9660.1%
Generation (MWh)609,873592,896,1760.1%
Wind capacity (MW)20243,9420.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Mesteno plant, and when do they retire?

1 operable generator totals 202 MW, with an average age of 6 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1202100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
MESOperatingOnshore Wind Turbine2022019n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Mesteno plant?

Mesteno Wind is the only joint owner reported for Mesteno, with 100.0%. Deriva Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Mesteno plant?

Mesteno is in Rio Grande City, Starr County, Texas, at 26.5237° N, 98.7455° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Texas are similar in size?

Texas has 228 operable wind plants with 43,942 MW of capacity, and Mesteno's 202 MW is 0% of that.

Wind plants in Texas around this size
PlantCountyMW2025 MWh
Penascal Wind Power LLCKenedy202297,617
Penascal II Wind Project LLCKenedy202286,270
Los Vientos Wind 1BCameron202370,330
MestenoStarr202609,873
Las Lomas Wind ProjectZapata202582,906
Stella Wind FarmKenedy201588,614
Diversion Wind Energy LLCBaylor201726,660

Source: EIA Forms EIA-860 and EIA-923, 2025.