Mojave 3/4/5 wind power plant, California

Mojave 3/4/5 is a 75 MW wind power plant in Kern County, California, operated by Terra-Gen Operating Co-Wind, and it generated 124,950 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 13th percentile of U.S. wind plants. By 2025 generation it ranks 3,148th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

75 MWNameplate capacity
21%Capacity factor, 2025, 13th percentile, on 67 MW net summer
0.1%Of CA generation, 2025
35 yearsAverage generator age, by MW

How hard does the Mojave 3/4/5 plant run compared with other wind plants?

The Mojave 3/4/5 plant had a capacity factor of 21% in 2025 on 67 MW of net summer capacity, the 13th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 78 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Mojave 3/4/521%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Mojave 3/4/5 plant generating more or less than last year?

Generation at Mojave 3/4/5 fell 5.9% from 2024 to 2025, from 132,783 MWh to 124,950 MWh.

Net generation by period
PeriodMWh
2024132,783
2025124,950
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20254,451
November 20253,095
October 20255,978
September 20257,340
August 202515,020
July 202515,946
June 202516,105
May 202518,039
April 202514,886
March 202511,282
February 20257,057
January 20255,751
December 20247,122
November 20246,727
October 202410,525
September 20249,742
August 202413,234
July 202411,188
June 202417,172
May 202416,396
April 202414,784
March 202411,105
February 20245,216
January 20249,572

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Mojave 3/4/5 plant?

Mojave 3/4/5 made 0.1% of the 204,542,898 MWh reported by California plants in 2025, from 0.1% of the state's 107,433 MW of capacity. By capacity it is the 335th largest of 1,877 plants in California, the 3,097th largest of 14,327 in the U.S. and the 780th largest of 1,358 wind plants. By 2025 generation it is the 324th largest of 1,608 generating plants in the state.

Mojave 3/4/5 within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)75107,4330.1%
Generation (MWh)124,950204,542,8980.1%
Wind capacity (MW)756,4791.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Mojave 3/4/5 plant, and when do they retire?

1 operable generator totals 75 MW, with an average age of 35 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1990s175100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingOnshore Wind Turbine751990n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Mojave 3/4/5 plant?

EIA lists no joint owners for Mojave 3/4/5. Terra-Gen Operating Co-Wind operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Mojave 3/4/5 plant?

Mojave 3/4/5 is in Mojave, Kern County, California, at 35.0506° N, 118.2572° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in California are similar in size?

California has 111 operable wind plants with 6,479 MW of capacity, and Mojave 3/4/5's 75 MW is 1% of that.

Wind plants in California around this size
PlantCountyMW2025 MWh
Rising Tree Wind FarmKern79250,358
Vasco WindsContra Costa78215,032
Montezuma Wind IISolano78195,762
Mojave 3/4/5Kern75124,950
Mountain View I & IIRiverside71275,228
Point WindKern65234,106
Whitewater Hill Wind PartnersRiverside62126,615