Point Wind is a 64.5 MW wind power plant in Kern County, California, operated by Terra-Gen Operating Co-Wind, and it generated 234,106 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 79th percentile of U.S. wind plants. By 2025 generation it ranks 2,301st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

64.5 MWNameplate capacity
41%Capacity factor, 2025, 79th percentile, on 64.5 MW net summer
0.1%Of CA generation, 2025
4 yearsAverage generator age, by MW

How hard does the Point Wind plant run compared with other wind plants?

The Point Wind plant had a capacity factor of 41% in 2025 on 64.5 MW of net summer capacity, the 79th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 151 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Point Wind41%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Point Wind plant generating more or less than last year?

Generation at Point Wind fell 2.2% from 2024 to 2025, from 239,312 MWh to 234,106 MWh. Through August 2026 it is running 11.9% behind the same months of 2025.

Net generation by period
PeriodMWh
2024239,312
2025234,106
2026 through August155,334
2025, same months176,336
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202616,560
July 202624,180
June 202627,777
May 202623,055
April 202623,508
March 202616,879
February 202611,887
January 202611,488
December 202515,814
November 202512,248
October 202515,676
September 202514,032
August 202521,403
July 202525,148
June 202525,023
May 202525,977
April 202523,514
March 202523,814
February 202517,493
January 202513,964
December 202413,305
November 202415,539
October 202414,981
September 202415,265
August 202420,883
July 202419,096
June 202428,649
May 202429,897
April 202423,763
March 202422,157
February 202416,131
January 202419,646

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Point Wind plant?

Point Wind made 0.1% of the 204,542,898 MWh reported by California plants in 2025, from 0.1% of the state's 107,433 MW of capacity. Its share of output is 1.9 times its share of capacity. By capacity it is the 364th largest of 1,877 plants in California, the 3,452nd largest of 14,327 in the U.S. and the 816th largest of 1,358 wind plants. By 2025 generation it is the 234th largest of 1,608 generating plants in the state.

Point Wind within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)65107,4330.1%
Generation (MWh)234,106204,542,8980.1%
Wind capacity (MW)656,4791.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Point Wind plant, and when do they retire?

1 operable generator totals 64.5 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s165100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
PW1OperatingOnshore Wind Turbine652021n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Point Wind plant?

EIA lists no joint owners for Point Wind. Terra-Gen Operating Co-Wind operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Point Wind plant?

Point Wind is in Tehachapi, Kern County, California, at 35.0808° N, 118.3614° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in California are similar in size?

California has 111 operable wind plants with 6,479 MW of capacity, and Point Wind's 64.5 MW is 1% of that.

Wind plants in California around this size
PlantCountyMW2025 MWh
Montezuma Wind IISolano78195,762
Mojave 3/4/5Kern75124,950
Mountain View I & IIRiverside71275,228
Point WindKern65234,106
Whitewater Hill Wind PartnersRiverside62126,615
Coachella Hills WindRiverside61219,258
Oasis WindKern60221,077