Skip to main content
RateWatt

Solar power plant, Montana

Mtsun solar power plant, Montana

Mtsun is a 80 MW solar power plant in Yellowstone County, Montana, operated by Greenbacker Renewable Energy Corporation, and it generated 149,035 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in Montana, and its capacity factor sits at the 35th percentile of U.S. solar plants. By 2025 generation it ranks 2,915th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

80 MWNameplate capacity
21%Capacity factor, 2025, 35th percentile, on 80 MW net summer
0.6%Of MT generation, 2025
2 yearsAverage generator age, by MW

How hard does the Mtsun plant run compared with other solar plants?

The Mtsun plant had a capacity factor of 21% in 2025 on 80 MW of net summer capacity, the 35th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 78 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Mtsun21%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Mtsun plant generating more or less than last year?

Generation at Mtsun fell 14.3% from 2024 to 2025, from 173,865 MWh to 149,035 MWh. Through August 2026 it is running 27.5% behind the same months of 2025.

Net generation by period
PeriodMWh
2024173,865
2025149,035
2026 through August84,581
2025, same months116,613
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202612,218
July 202614,540
June 202613,235
May 202613,815
April 202611,258
March 20268,747
February 20266,768
January 20264,000
December 20252,974
November 20254,700
October 202513,473
September 202511,275
August 202514,552
July 202514,323
June 202520,974
May 202521,234
April 202517,614
March 202512,401
February 20258,781
January 20256,734
December 20245,103
November 20246,915
October 202413,473
September 202416,165
August 202420,904
July 202422,277
June 202423,868
May 202418,526
April 202418,635
March 202412,758
February 20249,070
January 20246,171

Source: EIA Form EIA-923, through August 2026.

How much of Montana's electricity comes from the Mtsun plant?

Mtsun made 0.6% of the 26,725,203 MWh reported by Montana plants in 2025, from 1.0% of the state's 7,662 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 24th largest of 73 plants in Montana, the 2,965th largest of 14,327 in the U.S. and the 546th largest of 7,223 solar plants. By 2025 generation it is the 35th largest of 71 generating plants in the state.

Mtsun within Montana, 2025
MeasureThis plantMontanaShare
Capacity (MW)807,6621.0%
Generation (MWh)149,03526,725,2030.6%
Solar capacity (MW)8018144.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Mtsun plant, and when do they retire?

1 operable generator totals 80 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s180100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
MTSUNOperatingSolar Photovoltaic802023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Mtsun plant?

EIA lists no joint owners for Mtsun. Greenbacker Renewable Energy Corporation operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Mtsun plant?

Mtsun is in Billings, Yellowstone County, Montana, at 45.8560° N, 108.6020° W. It sits in the NorthWestern Energy (NWMT) balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Montana are similar in size?

Montana has 9 operable solar plants with 181 MW of capacity, and Mtsun's 80 MW is 44% of that.

Solar plants in Montana around this size
PlantCountyMW2025 MWh
MTSUNYellowstone80149,035
Apex SolarBeaverhead80164,724

Source: EIA Forms EIA-860 and EIA-923, 2025.