Natural gas power plant, Texas
Mustang Station Unit 4 natural gas power plant, Texas
Mustang Station Unit 4 is a 472 MW natural gas power plant in Yoakum County, Texas, operated by Golden Spread Electric Cooperative, Inc, and it generated 2,135,434 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Texas, and its capacity factor sits at the 73rd percentile of U.S. natural gas plants. By 2025 generation it ranks 485th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Mustang Station Unit 4 plant run compared with other natural gas plants?
The Mustang Station Unit 4 plant had a capacity factor of 53% in 2025 on 459 MW of net summer capacity, the 73rd percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 194 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Mustang Station Unit 4 | 53% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Mustang Station Unit 4 plant generating more or less than last year?
Generation at Mustang Station Unit 4 rose 26.2% from 2024 to 2025, from 1,691,776 MWh to 2,135,434 MWh.
| Period | MWh |
|---|---|
| 2024 | 1,691,776 |
| 2025 | 2,135,434 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 199,651 |
| November 2025 | 195,813 |
| October 2025 | 263,182 |
| September 2025 | 207,644 |
| August 2025 | 287,844 |
| July 2025 | 228,630 |
| June 2025 | 213,183 |
| May 2025 | 130,106 |
| April 2025 | 117,115 |
| March 2025 | 135,460 |
| February 2025 | 74,284 |
| January 2025 | 82,522 |
| December 2024 | 70,576 |
| November 2024 | 53,884 |
| October 2024 | 165,837 |
| September 2024 | 190,304 |
| August 2024 | 261,142 |
| July 2024 | 269,012 |
| June 2024 | 175,486 |
| May 2024 | 70,903 |
| April 2024 | 153,945 |
| March 2024 | 175,886 |
| February 2024 | 62,268 |
| January 2024 | 42,531 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Mustang Station Unit 4 plant, and when do they retire?
3 operable generators total 472 MW, with an average age of 16 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 2 | 306 | 65% | none reported |
| 2010s | 1 | 166 | 35% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Natural Gas Fired Combustion Turbine | 153 | 2006 | n/a |
| GEN2 | Operating | Natural Gas Fired Combustion Turbine | 153 | 2007 | n/a |
| GEN3 | Operating | Natural Gas Fired Combustion Turbine | 166 | 2013 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Mustang Station Unit 4 plant?
EIA lists no joint owners for Mustang Station Unit 4. Golden Spread Electric Cooperative, Inc operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Mustang Station Unit 4 plant?
Mustang Station Unit 4 is in Denver City, Yoakum County, Texas, at 32.9746° N, 102.7436° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Texas are similar in size?
Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Mustang Station Unit 4's 472 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Brotman Power Station | Brazoria | 484 | 298,742 |
| Remy Jade Power Station | Harris | 484 | 493,988 |
| Nichols | Potter | 475 | 1,665,814 |
| Mustang Station Unit 4 | Yoakum | 472 | 2,135,434 |
| Gregory Power Plant | San Patricio | 470 | 639,865 |
| Eastman Cogeneration Facility | Harrison | 468 | 2,640,665 |
| Texas City Power Plant | Galveston | 450 | 1,772,641 |