Nickajack is a 104 MW hydro power plant in Marion County, Tennessee, operated by Tennessee Valley Authority, and it generated 577,626 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.8% of the generation reported in Tennessee, and its capacity factor sits at the 97th percentile of U.S. hydro plants. By 2025 generation it ranks 1,169th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Nickajack plant run compared with other hydro plants?
The Nickajack plant had a capacity factor of 62% in 2025 on 106 MW of net summer capacity, the 97th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 228 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Nickajack | 62% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Nickajack plant generating more or less than last year?
Generation at Nickajack rose 17.6% from 2024 to 2025, from 491,171 MWh to 577,626 MWh.
| Period | MWh |
|---|---|
| 2024 | 491,171 |
| 2025 | 577,626 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 38,190 |
| November 2025 | 47,986 |
| October 2025 | 45,208 |
| September 2025 | 40,986 |
| August 2025 | 53,225 |
| July 2025 | 42,734 |
| June 2025 | 53,111 |
| May 2025 | 58,954 |
| April 2025 | 40,627 |
| March 2025 | 48,230 |
| February 2025 | 53,850 |
| January 2025 | 54,525 |
| December 2024 | 54,947 |
| November 2024 | 46,294 |
| October 2024 | 35,283 |
| September 2024 | 35,107 |
| August 2024 | 47,360 |
| July 2024 | 33,414 |
| June 2024 | 29,790 |
| May 2024 | 43,866 |
| April 2024 | 19,790 |
| March 2024 | 50,272 |
| February 2024 | 43,911 |
| January 2024 | 51,137 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Nickajack plant, and when do they retire?
4 operable generators total 104 MW, with an average age of 57 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1960s | 4 | 104 | 100% | none reported |
Every generator, 4 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 27 | 1968 | n/a |
| 2 | Operating | Conventional Hydroelectric | 28 | 1968 | n/a |
| 3 | Operating | Conventional Hydroelectric | 24 | 1968 | n/a |
| 4 | Operating | Conventional Hydroelectric | 24 | 1968 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Nickajack plant?
EIA lists no joint owners for Nickajack. Tennessee Valley Authority operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Nickajack plant?
Nickajack is in New Hope, Marion County, Tennessee, at 35.0017° N, 85.6218° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Tennessee are similar in size?
Tennessee has 28 operable hydro plants with 2,520 MW of capacity, and Nickajack's 104 MW is 4% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Cherokee Dam | Jefferson | 135 | 315,280 |
| Norris Dam | Anderson | 131 | 416,334 |
| Boone Dam | Sullivan | 106 | 145,459 |
| Nickajack | Marion | 104 | 577,626 |
| Old Hickory | Sumner | 104 | 324,741 |
| Cordell Hull | Smith | 100 | 441,299 |
| Apalachia | Polk | 94 | 389,144 |
Source: EIA Forms EIA-860 and EIA-923, 2025.