Oak Creek Energy Systems I is a 34.5 MW wind power plant in Kern County, California, operated by Terra-Gen Operating Co-Wind, and it generated 57,279 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 9th percentile of U.S. wind plants. By 2025 generation it ranks 3,919th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Oak Creek Energy Systems I plant run compared with other wind plants?
The Oak Creek Energy Systems I plant had a capacity factor of 19% in 2025 on 34.5 MW of net summer capacity, the 9th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 69 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Oak Creek Energy Systems I | 19% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Oak Creek Energy Systems I plant generating more or less than last year?
Generation at Oak Creek Energy Systems I rose 5.1% from 2024 to 2025, from 54,496 MWh to 57,279 MWh.
| Period | MWh |
|---|---|
| 2024 | 54,496 |
| 2025 | 57,279 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 2,521 |
| November 2025 | 1,973 |
| October 2025 | 3,515 |
| September 2025 | 3,030 |
| August 2025 | 5,495 |
| July 2025 | 5,831 |
| June 2025 | 7,299 |
| May 2025 | 8,200 |
| April 2025 | 6,078 |
| March 2025 | 6,018 |
| February 2025 | 4,489 |
| January 2025 | 2,830 |
| December 2024 | 3,125 |
| November 2024 | 3,120 |
| October 2024 | 2,453 |
| September 2024 | 3,636 |
| August 2024 | 4,666 |
| July 2024 | 3,862 |
| June 2024 | 6,934 |
| May 2024 | 8,293 |
| April 2024 | 6,390 |
| March 2024 | 5,517 |
| February 2024 | 2,129 |
| January 2024 | 4,371 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Oak Creek Energy Systems I plant, and when do they retire?
4 operable generators total 34.5 MW, with an average age of 28 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1980s | 1 | 4 | 10% | none reported |
| 1990s | 3 | 31 | 90% | none reported |
Every generator, 4 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Onshore Wind Turbine | 4 | 1982 | n/a |
| GEN2 | Operating | Onshore Wind Turbine | 4 | 1993 | n/a |
| GEN3 | Operating | Onshore Wind Turbine | 23 | 1999 | n/a |
| GEN4 | Operating | Onshore Wind Turbine | 4 | 1999 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Oak Creek Energy Systems I plant?
EIA lists no joint owners for Oak Creek Energy Systems I. Terra-Gen Operating Co-Wind operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Oak Creek Energy Systems I plant?
Oak Creek Energy Systems I is in Mojave, Kern County, California, at 35.0439° N, 118.2764° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in California are similar in size?
California has 111 operable wind plants with 6,479 MW of capacity, and Oak Creek Energy Systems I's 34.5 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Salka Cabazon Wind | Riverside | 39 | 12,772 |
| Buena Vista Energy LLC | Contra Costa | 38 | 96,146 |
| FPL Energy Montezuma Winds LLC | Solano | 37 | 95,503 |
| Oak Creek Energy Systems I | Kern | 35 | 57,279 |
| San Gorgonio Farms Wind Farm | Riverside | 31 | 51,676 |
| Mesa Wind Power LLC | Riverside | 30 | 122,796 |
| Ridgetop Energy LLC | Kern | 29 | 24,474 |
Source: EIA Forms EIA-860 and EIA-923, 2025.