Biomass power plant, Ohio
Pixelle Specialty Solutions LLC-Chilli biomass power plant, Ohio
Pixelle Specialty Solutions LLC-Chilli is a 92.8 MW power plant, 65.6 MW of it biomass, in Ross County, Ohio, operated by US Paper Mill Company, and it generated 114,038 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Ohio, and its capacity factor sits at the 5th percentile of U.S. biomass plants. By 2025 generation it ranks 3,265th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Pixelle Specialty Solutions LLC-Chilli plant run compared with other biomass plants?
The Pixelle Specialty Solutions LLC-Chilli plant's biomass units had a capacity factor of 19% in 2025 on 37.1 MW of net summer capacity, the 5th percentile of the 167 U.S. biomass plants with at least 20 MW. The typical biomass plant reached 48%. That equals about 70 days at full output out of 365.
0%Shaded: the middle half of biomass plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Pixelle Specialty Solutions LLC-Chilli | 19% |
| Biomass plants, 75th percentile | 65% |
| Biomass plants, median | 48% |
| Biomass plants, 25th percentile | 35% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its biomass generators only. Values above 105% are left out of the comparison.
Is the Pixelle Specialty Solutions LLC-Chilli plant generating more or less than last year?
Pixelle Specialty Solutions LLC-Chilli generated 114,038 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 100.0% behind the same months of 2025. Only 1 months of 2026 have been reported for this plant. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 237,475 |
| 2025 | 114,038 |
| 2026 through August | 0 |
| 2025, same months | 26,260 |
Monthly generation, Jan 2024 to Feb 2026
| Month | MWh |
|---|---|
| February 2026 | 0 |
| December 2025 | 0 |
| November 2025 | 0 |
| June 2025 | 25,080 |
| May 2025 | 30,853 |
| April 2025 | 31,845 |
| February 2025 | 26,260 |
| December 2024 | 34,505 |
| November 2024 | 31,267 |
| October 2024 | 32,808 |
| September 2024 | 18,662 |
| August 2024 | 21,626 |
| July 2024 | 19,989 |
| June 2024 | 16,380 |
| May 2024 | 16,140 |
| March 2024 | 16,943 |
| February 2024 | 4,290 |
| January 2024 | 24,865 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Pixelle Specialty Solutions LLC-Chilli plant, and when do they retire?
4 operable generators total 92.8 MW, with an average age of 59 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1950s | 2 | 35 | 37% | none reported |
| 1960s | 1 | 31 | 33% | none reported |
| 1970s | 1 | 27 | 29% | none reported |
Every generator, 4 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| T-10 | Out of service | Wood/Wood Waste Biomass | 11 | 1952 | n/a |
| T-11 | Operating | Wood/Wood Waste Biomass | 24 | 1958 | n/a |
| T-12 | Operating | Wood/Wood Waste Biomass | 31 | 1967 | n/a |
| T-13 | Operating | Natural Gas Steam Turbine | 27 | 1978 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Pixelle Specialty Solutions LLC-Chilli plant?
EIA lists no joint owners for Pixelle Specialty Solutions LLC-Chilli. US Paper Mill Company operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What fuels does the Pixelle Specialty Solutions LLC-Chilli plant use?
Pixelle Specialty Solutions LLC-Chilli has capacity on 2 fuels: 71% biomass and 29% natural gas. In 2025, biomass made 55% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Biomass | 66 | 70.7% | 62,499 |
| Natural gas | 27 | 29.3% | 49,375 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Pixelle Specialty Solutions LLC-Chilli plant?
Pixelle Specialty Solutions LLC-Chilli is in Chillicothe, Ross County, Ohio, at 39.3246° N, 82.9740° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.