Solar power plant, Florida
Rattler Solar Plant, Florida
Rattler Solar Plant is a 74.9 MW solar power plant in Hernando County, Florida, operated by Duke Energy Florida, LLC, and it generated 22,684 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 4th percentile of U.S. solar plants. By 2025 generation it ranks 5,093rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does Rattler Solar Plant run compared with other solar plants?
Rattler Solar Plant had a capacity factor of 3% in 2025 on 74.9 MW of net summer capacity, the 4th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 13 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Rattler Solar Plant | 3% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is Rattler Solar Plant generating more or less than last year?
Rattler Solar Plant generated 22,684 MWh in 2025; EIA reports no 2024 total to compare.
| Period | MWh |
|---|---|
| 2024 | n/a |
| 2025 | 22,684 |
| 2026 through August | 126,138 |
Monthly generation, Nov 2025 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 16,180 |
| July 2026 | 16,857 |
| June 2026 | 17,574 |
| May 2026 | 17,527 |
| April 2026 | 15,346 |
| March 2026 | 17,073 |
| February 2026 | 13,747 |
| January 2026 | 11,834 |
| December 2025 | 10,620 |
| November 2025 | 12,064 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at Rattler Solar Plant, and when do they retire?
1 operable generator totals 74.9 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 75 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| RTLR1 | Operating | Solar Photovoltaic | 75 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns Rattler Solar Plant?
EIA lists no joint owners for Rattler Solar Plant. Duke Energy Florida, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Duke Energy Florida, LLC charge homes?
Duke Energy Florida, LLC, the operator of Rattler Solar Plant, had an average residential price of 18.36¢ per kWh and an average bill of $185 a month in 2025, 21% above the Florida average of 15.21¢.
| Measure | Price | Monthly bill | Against Florida |
|---|---|---|---|
| Duke Energy Florida, LLC | 18.36¢ | $185 | 21% higher |
| Florida average | 15.21¢ | $168 | |
| U.S. average | 17.23¢ | $151 | 13% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is Rattler Solar Plant?
Rattler Solar Plant is in Brookesville, Hernando County, Florida, at 28.6343° N, 82.2887° W. It sits in the Duke Energy Florida Inc balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Florida are similar in size?
Florida has 210 operable solar plants with 12,223 MW of capacity, and Rattler Solar Plant's 74.9 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Falmouth Renewable Energy Center | Suwannee | 75 | 180,960 |
| County Line Renewable Energy Center | Gilchrist | 75 | 186,587 |
| Sundance Renewable Energy Center | Madison | 75 | 88,149 |
| Rattler Solar Plant | Hernando | 75 | 22,684 |
| Half Moon Solar Plant | Sumter | 75 | 23,687 |
| Wimauma Solar and Battery Storage | Hillsborough | 75 | 108,115 |
| Babcock Solar Energy Center Hybrid | Charlotte | 75 | 134,873 |
Source: EIA Forms EIA-860 and EIA-923, 2025.