Hydro power plant, Oklahoma
Robert S Kerr hydroelectric power plant, Oklahoma
Robert S Kerr is a 110 MW hydro power plant in Sequoyah County, Oklahoma, operated by USCE-Tulsa District, and it generated 449,593 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in Oklahoma, and its capacity factor sits at the 85th percentile of U.S. hydro plants. By 2025 generation it ranks 1,452nd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Robert S Kerr plant run compared with other hydro plants?
The Robert S Kerr plant had a capacity factor of 49% in 2025 on 106 MW of net summer capacity, the 85th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 177 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Robert S Kerr | 49% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Robert S Kerr plant generating more or less than last year?
Generation at Robert S Kerr rose 21.4% from 2024 to 2025, from 370,327 MWh to 449,593 MWh.
| Period | MWh |
|---|---|
| 2024 | 370,327 |
| 2025 | 449,593 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 20,413 |
| November 2025 | 24,478 |
| October 2025 | 29,580 |
| September 2025 | 40,571 |
| August 2025 | 52,228 |
| July 2025 | 51,365 |
| June 2025 | 45,421 |
| May 2025 | 49,566 |
| April 2025 | 48,006 |
| March 2025 | 39,402 |
| February 2025 | 22,889 |
| January 2025 | 25,674 |
| December 2024 | 28,995 |
| November 2024 | 46,610 |
| October 2024 | 6,123 |
| September 2024 | 11,995 |
| August 2024 | 22,042 |
| July 2024 | 23,127 |
| June 2024 | 49,656 |
| May 2024 | 47,083 |
| April 2024 | 27,518 |
| March 2024 | 25,671 |
| February 2024 | 38,762 |
| January 2024 | 42,745 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Robert S Kerr plant, and when do they retire?
4 operable generators total 110 MW, with an average age of 54 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 4 | 110 | 100% | none reported |
Every generator, 4 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 28 | 1971 | n/a |
| 2 | Operating | Conventional Hydroelectric | 28 | 1971 | n/a |
| 3 | Out of service | Conventional Hydroelectric | 28 | 1971 | n/a |
| 4 | Operating | Conventional Hydroelectric | 28 | 1971 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Robert S Kerr plant?
EIA lists no joint owners for Robert S Kerr. USCE-Tulsa District operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Robert S Kerr plant?
Robert S Kerr is in Keota, Sequoyah County, Oklahoma, at 35.3445° N, 94.7755° W. It sits in the Southwestern Power Administration balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Oklahoma are similar in size?
Oklahoma has 10 operable hydro plants with 824 MW of capacity, and Robert S Kerr's 110 MW is 13% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Pensacola | Mayes | 130 | 422,247 |
| Markham | Mayes | 128 | 288,136 |
| Robert S Kerr | Sequoyah | 110 | 449,593 |
| Broken Bow Dam | McCurtain | 100 | 195,671 |
| Eufaula Dam | Haskell | 90 | 294,034 |
| Webbers Falls | Muskogee | 75 | 205,181 |
Source: EIA Forms EIA-860 and EIA-923, 2025.