Hydro power plant, Oklahoma
Webbers Falls hydroelectric power plant, Oklahoma
Webbers Falls is a 75 MW hydro power plant in Muskogee County, Oklahoma, operated by USCE-Tulsa District, and it generated 205,181 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Oklahoma, and its capacity factor sits at the 45th percentile of U.S. hydro plants. By 2025 generation it ranks 2,458th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Webbers Falls plant run compared with other hydro plants?
The Webbers Falls plant had a capacity factor of 31% in 2025 on 75 MW of net summer capacity, the 45th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 114 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Webbers Falls | 31% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Webbers Falls plant generating more or less than last year?
Generation at Webbers Falls rose 17.7% from 2024 to 2025, from 174,272 MWh to 205,181 MWh.
| Period | MWh |
|---|---|
| 2024 | 174,272 |
| 2025 | 205,181 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 9,357 |
| November 2025 | 13,661 |
| October 2025 | 14,467 |
| September 2025 | 20,074 |
| August 2025 | 29,141 |
| July 2025 | 26,526 |
| June 2025 | 20,969 |
| May 2025 | 12,423 |
| April 2025 | 22,364 |
| March 2025 | 21,559 |
| February 2025 | 7,282 |
| January 2025 | 7,358 |
| December 2024 | 9,719 |
| November 2024 | 25,396 |
| October 2024 | 1,382 |
| September 2024 | 3,717 |
| August 2024 | 8,378 |
| July 2024 | 11,602 |
| June 2024 | 25,900 |
| May 2024 | 21,657 |
| April 2024 | 14,106 |
| March 2024 | 11,068 |
| February 2024 | 20,265 |
| January 2024 | 21,082 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Webbers Falls plant, and when do they retire?
3 operable generators total 75 MW, with an average age of 52 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1970s | 3 | 75 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Out of service | Conventional Hydroelectric | 25 | 1973 | n/a |
| 2 | Operating | Conventional Hydroelectric | 25 | 1973 | n/a |
| 3 | Operating | Conventional Hydroelectric | 25 | 1973 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Webbers Falls plant?
EIA lists no joint owners for Webbers Falls. USCE-Tulsa District operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Webbers Falls plant?
Webbers Falls is in Webbers Falls, Muskogee County, Oklahoma, at 35.5531° N, 95.1708° W. It sits in the Southwestern Power Administration balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Oklahoma are similar in size?
Oklahoma has 10 operable hydro plants with 824 MW of capacity, and Webbers Falls' 75 MW is 9% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Robert S Kerr | Sequoyah | 110 | 449,593 |
| Broken Bow Dam | McCurtain | 100 | 195,671 |
| Eufaula Dam | Haskell | 90 | 294,034 |
| Webbers Falls | Muskogee | 75 | 205,181 |
| Keystone Dam | Tulsa | 70 | 293,344 |
| Fort Gibson | Cherokee | 45 | 217,257 |
| Tenkiller Ferry | Sequoyah | 39 | 11,015 |
Source: EIA Forms EIA-860 and EIA-923, 2025.