Hydro power plant, Oregon
Round Butte hydroelectric power plant, Oregon
Round Butte is a 373 MW hydro power plant in Jefferson County, Oregon, operated by Portland General Electric Co, and it generated 772,426 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.2% of the generation reported in Oregon, and its capacity factor sits at the 31st percentile of U.S. hydro plants. By 2025 generation it ranks 908th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Round Butte plant run compared with other hydro plants?
The Round Butte plant had a capacity factor of 25% in 2025 on 353 MW of net summer capacity, the 31st percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 91 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Round Butte | 25% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Round Butte plant generating more or less than last year?
Generation at Round Butte fell 2.8% from 2024 to 2025, from 794,421 MWh to 772,426 MWh.
1 month shows net generation below zero, when the plant used more power than it sent out, so the months are listed below rather than charted.
| Period | MWh |
|---|---|
| 2024 | 794,421 |
| 2025 | 772,426 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 55,671 |
| November 2025 | -137 |
| October 2025 | 714 |
| September 2025 | 64,963 |
| August 2025 | 58,798 |
| July 2025 | 61,112 |
| June 2025 | 64,195 |
| May 2025 | 71,779 |
| April 2025 | 100,516 |
| March 2025 | 125,185 |
| February 2025 | 81,002 |
| January 2025 | 88,628 |
| December 2024 | 49,626 |
| November 2024 | 62,775 |
| October 2024 | 60,912 |
| September 2024 | 54,767 |
| August 2024 | 59,387 |
| July 2024 | 56,338 |
| June 2024 | 59,816 |
| May 2024 | 66,423 |
| April 2024 | 76,300 |
| March 2024 | 79,324 |
| February 2024 | 94,016 |
| January 2024 | 74,737 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Round Butte plant, and when do they retire?
3 operable generators total 373 MW, with an average age of 61 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1960s | 3 | 373 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 113 | 1964 | n/a |
| 2 | Operating | Conventional Hydroelectric | 130 | 1964 | n/a |
| 3 | Operating | Conventional Hydroelectric | 130 | 1964 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Round Butte plant?
2 owners report shares in Round Butte; Portland General Electric Co holds the largest named share, 50.1% or about 187 MW. Portland General Electric Co operates the plant.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| Portland General Electric Co | 50.1% | 187 | 386,985 |
| Warm Springs Power Enterprises | 49.9% | 186 | 385,441 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
What does Portland General Electric Co charge homes?
Portland General Electric Co, the operator of Round Butte, had an average residential price of 18.79¢ per kWh and an average bill of $142 a month in 2025, 22% above the Oregon average of 15.46¢.
| Measure | Price | Monthly bill | Against Oregon |
|---|---|---|---|
| Portland General Electric Co | 18.79¢ | $142 | 22% higher |
| Oregon average | 15.46¢ | $134 | |
| U.S. average | 17.23¢ | $151 | 11% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Round Butte plant?
Round Butte is in Madras, Jefferson County, Oregon, at 44.6058° N, 121.2773° W. It sits in the Portland General Electric Company balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Oregon are similar in size?
Oregon has 63 operable hydro plants with 8,360 MW of capacity, and Round Butte's 373 MW is 4% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Hells Canyon | Wallowa | 411 | 2,025,144 |
| Round Butte | Jefferson | 373 | 772,426 |
| Oxbow (OR) | Baker | 190 | 990,285 |
Source: EIA Forms EIA-860 and EIA-923, 2025.