Wind power plant, Idaho
Sawtooth Wind Project, Idaho
Sawtooth Wind Project is a 22.4 MW wind power plant in Elmore County, Idaho, operated by Idaho Winds LLC, and it generated 49,850 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Idaho, and its capacity factor sits at the 23rd percentile of U.S. wind plants. By 2025 generation it ranks 4,093rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Sawtooth Wind Project plant run compared with other wind plants?
The Sawtooth Wind Project plant had a capacity factor of 25% in 2025 on 22.4 MW of net summer capacity, the 23rd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 93 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Sawtooth Wind Project | 25% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Sawtooth Wind Project plant generating more or less than last year?
Generation at Sawtooth Wind Project fell 17.3% from 2024 to 2025, from 60,272 MWh to 49,850 MWh.
| Period | MWh |
|---|---|
| 2024 | 60,272 |
| 2025 | 49,850 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 3,935 |
| November 2025 | 3,266 |
| October 2025 | 4,913 |
| September 2025 | 3,283 |
| August 2025 | 3,283 |
| July 2025 | 3,649 |
| June 2025 | 4,172 |
| May 2025 | 5,473 |
| April 2025 | 3,569 |
| March 2025 | 4,827 |
| February 2025 | 4,974 |
| January 2025 | 4,506 |
| December 2024 | 4,381 |
| November 2024 | 5,870 |
| October 2024 | 4,504 |
| September 2024 | 3,297 |
| August 2024 | 3,849 |
| July 2024 | 3,233 |
| June 2024 | 4,387 |
| May 2024 | 6,827 |
| April 2024 | 6,728 |
| March 2024 | 4,487 |
| February 2024 | 5,554 |
| January 2024 | 7,155 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Sawtooth Wind Project plant, and when do they retire?
1 operable generator totals 22.4 MW, with an average age of 14 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 22 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| ST | Operating | Onshore Wind Turbine | 22 | 2011 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Sawtooth Wind Project plant?
EIA lists no joint owners for Sawtooth Wind Project. Idaho Winds LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Sawtooth Wind Project plant?
Sawtooth Wind Project is in Glenns Ferry, Elmore County, Idaho, at 42.9822° N, 115.3933° W. It sits in the Idaho Power Company balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Idaho are similar in size?
Idaho has 33 operable wind plants with 1,132 MW of capacity, and Sawtooth Wind Project's 22.4 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Camp Reed | Elmore | 23 | 59,005 |
| Power County Wind Park South | Power | 23 | 56,756 |
| Power County Wind Park North | Power | 23 | 63,858 |
| Sawtooth Wind Project | Elmore | 22 | 49,850 |
| Burley Butte Windpark | Cassia | 21 | 55,989 |
| Salmon Falls Wind Park | Twin Falls | 21 | 58,267 |
| Mountain Home | Elmore | 21 | 33,053 |
Source: EIA Forms EIA-860 and EIA-923, 2025.