Snipesville is a 86 MW solar power plant in Jeff Davis County, Georgia, operated by SR Snipesville, LLC, and it generated 207,194 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Georgia, and its capacity factor sits at the 80th percentile of U.S. solar plants. By 2025 generation it ranks 2,441st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

86 MWNameplate capacity
28%Capacity factor, 2025, 80th percentile, on 86 MW net summer
0.1%Of GA generation, 2025
5 yearsAverage generator age, by MW

How hard does the Snipesville plant run compared with other solar plants?

The Snipesville plant had a capacity factor of 28% in 2025 on 86 MW of net summer capacity, the 80th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 100 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Snipesville28%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Snipesville plant generating more or less than last year?

Generation at Snipesville rose 15.1% from 2024 to 2025, from 180,065 MWh to 207,194 MWh. Through August 2026 it is running 20.2% behind the same months of 2025.

Net generation by period
PeriodMWh
2024180,065
2025207,194
2026 through August120,570
2025, same months151,035
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202617,020
July 202621,841
June 20264,139
May 202619,144
April 202621,792
March 202615,564
February 20269,604
January 202611,466
December 20259,398
November 202514,410
October 202514,049
September 202518,302
August 202516,851
July 202524,589
June 202520,980
May 202520,564
April 202521,907
March 202522,043
February 202512,576
January 202511,525
December 20249,341
November 20248,850
October 202413,359
September 202410,885
August 202421,141
July 202419,889
June 202422,255
May 202419,383
April 202420,131
March 202412,642
February 202411,434
January 202410,755

Source: EIA Form EIA-923, through August 2026.

How much of Georgia's electricity comes from the Snipesville plant?

Snipesville made 0.1% of the 144,967,352 MWh reported by Georgia plants in 2025, from 0.2% of the state's 42,719 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 64th largest of 263 plants in Georgia, the 2,895th largest of 14,327 in the U.S. and the 514th largest of 7,223 solar plants. By 2025 generation it is the 54th largest of 242 generating plants in the state.

Snipesville within Georgia, 2025
MeasureThis plantGeorgiaShare
Capacity (MW)8642,7190.2%
Generation (MWh)207,194144,967,3520.1%
Solar capacity (MW)865,4141.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Snipesville plant, and when do they retire?

1 operable generator totals 86 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s186100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
SNIPEOperatingSolar Photovoltaic862020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Snipesville plant?

EIA lists no joint owners for Snipesville. SR Snipesville, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Snipesville plant?

Snipesville is in Denton, Jeff Davis County, Georgia, at 31.7158° N, 82.7495° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Georgia are similar in size?

Georgia has 152 operable solar plants with 5,414 MW of capacity, and Snipesville's 86 MW is 2% of that.

Solar plants in Georgia around this size
PlantCountyMW2025 MWh
SR Arlington IIEarly103228,798
White Pine Solar, LLCTaylor101187,859
SR LumpkinStewart100234,505
SnipesvilleJeff Davis86207,194
Decatur Parkway Solar Project, LLCDecatur80173,151
Lancaster Solar GARandolph80183,115
Blackwater SolarWare80188,661