Wind power plant, Maine
Stetson Wind II power plant, Maine
Stetson Wind II is a 25.5 MW wind power plant in Washington County, Maine, operated by Evergreen Wind, LLC, and it generated 55,303 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Maine, and its capacity factor sits at the 21st percentile of U.S. wind plants. By 2025 generation it ranks 3,967th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Stetson Wind II plant run compared with other wind plants?
The Stetson Wind II plant had a capacity factor of 25% in 2025 on 25.5 MW of net summer capacity, the 21st percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 90 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Stetson Wind II | 25% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Stetson Wind II plant generating more or less than last year?
Generation at Stetson Wind II rose 11.4% from 2024 to 2025, from 49,655 MWh to 55,303 MWh.
| Period | MWh |
|---|---|
| 2024 | 49,655 |
| 2025 | 55,303 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 5,681 |
| November 2025 | 5,990 |
| October 2025 | 4,703 |
| September 2025 | 2,658 |
| August 2025 | 2,960 |
| July 2025 | 3,352 |
| June 2025 | 3,216 |
| May 2025 | 3,603 |
| April 2025 | 4,708 |
| March 2025 | 5,846 |
| February 2025 | 6,203 |
| January 2025 | 6,383 |
| December 2024 | 4,776 |
| November 2024 | 6,302 |
| October 2024 | 4,990 |
| September 2024 | 3,160 |
| August 2024 | 2,465 |
| July 2024 | 2,589 |
| June 2024 | 3,466 |
| May 2024 | 2,531 |
| April 2024 | 4,521 |
| March 2024 | 5,843 |
| February 2024 | 4,957 |
| January 2024 | 4,055 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Stetson Wind II plant, and when do they retire?
1 operable generator totals 25.5 MW, with an average age of 15 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 26 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 26 | 2010 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Stetson Wind II plant?
EIA lists no joint owners for Stetson Wind II. Evergreen Wind, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Stetson Wind II plant?
Stetson Wind II is in Danforth, Washington County, Maine, at 45.6150° N, 67.9710° W. It sits in the ISO New England Inc. balancing area (NERC region NPCC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Maine are similar in size?
Maine has 22 operable wind plants with 1,217 MW of capacity, and Stetson Wind II's 25.5 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Mars Hill Wind Farm Project | Aroostook | 42 | 128,290 |
| Bull Hill Wind Project | Hancock | 35 | 66,494 |
| Saddleback Ridge Wind Farm | Franklin | 34 | 90,411 |
| Stetson Wind II | Washington | 26 | 55,303 |
| Canton Mountain Wind | Oxford | 23 | 56,392 |
| Spruce Mountain WInd | Oxford | 20 | 52,563 |
| Silver Maple | Penobscot | 20 | 63,882 |
Source: EIA Forms EIA-860 and EIA-923, 2025.