Natural gas power plant, Texas
Tenaska Frontier Generation Station, Texas
Tenaska Frontier Generation Station is a 940 MW natural gas power plant in Grimes County, Texas, operated by Tenaska Frontier Partners Ltd, and it generated 3,503,759 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in Texas, and its capacity factor sits at the 69th percentile of U.S. natural gas plants. By 2025 generation it ranks 337th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does Tenaska Frontier Generation Station run compared with other natural gas plants?
Tenaska Frontier Generation Station had a capacity factor of 47% in 2025 on 860 MW of net summer capacity, the 69th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 170 days at full output out of 365.
0%Shaded: the middle half of natural gas plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Tenaska Frontier Generation Station | 47% |
| Natural gas plants, 75th percentile | 56% |
| Natural gas plants, median | 22% |
| Natural gas plants, 25th percentile | 6% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is Tenaska Frontier Generation Station generating more or less than last year?
Generation at Tenaska Frontier Generation Station fell 18.5% from 2024 to 2025, from 4,297,007 MWh to 3,503,759 MWh. Through August 2026 it is running 70.4% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 4,297,007 |
| 2025 | 3,503,759 |
| 2026 through August | 3,057,784 |
| 2025, same months | 1,794,542 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 546,006 |
| July 2026 | 538,137 |
| June 2026 | 498,098 |
| May 2026 | 539,081 |
| April 2026 | 388,096 |
| March 2026 | 10,101 |
| February 2026 | 239,791 |
| January 2026 | 298,474 |
| December 2025 | 380,000 |
| November 2025 | 262,820 |
| October 2025 | 539,626 |
| September 2025 | 526,771 |
| August 2025 | 497,204 |
| July 2025 | 497,893 |
| June 2025 | 166,984 |
| May 2025 | 0 |
| April 2025 | 0 |
| March 2025 | 0 |
| February 2025 | 259,698 |
| January 2025 | 372,763 |
| December 2024 | 360,029 |
| November 2024 | 363,206 |
| October 2024 | 220,556 |
| September 2024 | 501,214 |
| August 2024 | 549,267 |
| July 2024 | 513,720 |
| June 2024 | 497,992 |
| May 2024 | 362,629 |
| April 2024 | 277 |
| March 2024 | 342,910 |
| February 2024 | 187,561 |
| January 2024 | 397,646 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at Tenaska Frontier Generation Station, and when do they retire?
4 operable generators total 940 MW, with an average age of 25 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 4 | 940 | 100% | none reported |
Every generator, 4 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GTG1 | Operating | Natural Gas Fired Combined Cycle | 183 | 2000 | n/a |
| GTG2 | Operating | Natural Gas Fired Combined Cycle | 183 | 2000 | n/a |
| GTG3 | Operating | Natural Gas Fired Combined Cycle | 183 | 2000 | n/a |
| STG1 | Operating | Natural Gas Fired Combined Cycle | 390 | 2000 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns Tenaska Frontier Generation Station?
5 owners report shares in Tenaska Frontier Generation Station; Tanaska Grimes Partners LP holds the largest named share, 74.3% or about 698 MW. Tenaska Frontier Partners Ltd operates the plant.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| Tanaska Grimes Partners LP | 74.3% | 698 | 2,601,541 |
| Montana Grimes Frontier LP | 24.8% | 233 | 867,180 |
| Tenaska VI Partners LP | 0.5% | 4 | 16,468 |
| Diamond Frontier LLC | 0.3% | 3 | 9,811 |
| Montana Grimes County LLC | 0.3% | 2 | 8,759 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
Where is Tenaska Frontier Generation Station?
Tenaska Frontier Generation Station is in Shiro, Grimes County, Texas, at 30.5924° N, 95.9178° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which natural gas plants in Texas are similar in size?
Texas has 305 operable natural gas plants with 81,574 MW of capacity, and Tenaska Frontier Generation Station's 940 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Freestone Energy Center | Freestone | 1,036 | 6,479,914 |
| Montgomery County | Montgomery | 1,000 | 5,870,260 |
| Hays Energy Project | Hays | 989 | 5,338,430 |
| Tenaska Frontier Generation Station | Grimes | 940 | 3,503,759 |
| Tenaska Gateway Generating Station | Rusk | 940 | 4,708,795 |
| Formosa Utility Venture Ltd | Calhoun | 933 | 4,865,486 |
| Baytown Energy Center | Chambers | 933 | 3,746,903 |
Source: EIA Forms EIA-860 and EIA-923, 2025.