Wind power plant, Pennsylvania
Twin Ridges Wind Farm, Pennsylvania
Twin Ridges Wind Farm is a 139 MW wind power plant in Somerset County, Pennsylvania, operated by Exus Pennsylvania Wind Holdings, and it generated 510,568 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Pennsylvania, and its capacity factor sits at the 81st percentile of U.S. wind plants. By 2025 generation it ranks 1,316th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Twin Ridges Wind Farm plant run compared with other wind plants?
The Twin Ridges Wind Farm plant had a capacity factor of 42% in 2025 on 139 MW of net summer capacity, the 81st percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 153 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Twin Ridges Wind Farm | 42% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Twin Ridges Wind Farm plant generating more or less than last year?
Twin Ridges Wind Farm generated 510,568 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 8 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 273,905 |
| 2025 | 510,568 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 57,968 |
| November 2025 | 57,673 |
| October 2025 | 44,230 |
| September 2025 | 15,990 |
| August 2025 | 20,749 |
| July 2025 | 20,942 |
| June 2025 | 29,677 |
| May 2025 | 49,119 |
| April 2025 | 49,908 |
| March 2025 | 60,917 |
| February 2025 | 44,489 |
| January 2025 | 58,906 |
| December 2024 | 47,637 |
| November 2024 | 45,037 |
| October 2024 | 0 |
| September 2024 | 0 |
| August 2024 | 0 |
| July 2024 | 0 |
| June 2024 | 2,227 |
| May 2024 | 10,246 |
| April 2024 | 36,811 |
| March 2024 | 51,078 |
| February 2024 | 32,501 |
| January 2024 | 48,368 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Twin Ridges Wind Farm plant, and when do they retire?
1 operable generator totals 139 MW, with an average age of 13 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 139 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 139 | 2012 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Twin Ridges Wind Farm plant?
EIA lists no joint owners for Twin Ridges Wind Farm. Exus Pennsylvania Wind Holdings operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Twin Ridges Wind Farm plant?
Twin Ridges Wind Farm is in Meyersdale, Somerset County, Pennsylvania, at 39.7606° N, 78.8747° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Pennsylvania are similar in size?
Pennsylvania has 27 operable wind plants with 1,556 MW of capacity, and Twin Ridges Wind Farm's 139 MW is 9% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Mehoopany Wind Energy LLC | Wyoming | 141 | 307,023 |
| Twin Ridges Wind Farm | Somerset | 139 | 510,568 |
| Locust Ridge II LLC | Schuylkill | 102 | 198,680 |
| Armenia Mountain Wind Farm | Tioga | 101 | 265,176 |
| Big Level Wind | Potter | 90 | 298,316 |
Source: EIA Forms EIA-860 and EIA-923, 2025.